4615 N WILLOW CREST AVE 91602
Certificate Information: 4615 N WILLOW CREST AVE 91602
- Application / Permit
- 18016-20000-20897
- Plan Check / Job No.
- B18VN11227
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' x 41'6" GARAGE/STORSGE TO ACCESSORY DWELLING UNIT PER AB494 AND SB229
- Permit Issued
- Issued on 5/26/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2018 | JEFFREY TANGONAN |
| Corrections Issued | 6/29/2018 | JEFFREY TANGONAN |
| Plan Check Approved | 5/15/2020 | JEFFREY TANGONAN |
| Issued | 5/26/2020 | LADBS |
| Building Plans Picked Up | 5/29/2020 | APPLICANT |
| CofO in Progress | 10/26/2021 | ARAM AVEDISIAN |
| Permit Finaled | 10/27/2021 | MICHAEL SMITH |
| CofO Issued | 10/27/2021 | MICHAEL SMITH |
| Permit Finaled | 10/27/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/17/2018 | EDUARDO PEDROZA |
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2018 | EDUARDO PEDROZA |
| Sewer availability | Cleared | 7/17/2018 | EDUARDO PEDROZA |
| Construction near power lines | Cleared | 2/22/2019 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/22/2019 | RIDWAN HARDY |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Butel Construction Inc; Lic. No.: 852273-B | 257 SOUTH CITRUS AVE LOS ANGELES, CA 90036 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/26/2020 | Partial Approval | THOMAS FINNILA |
| Underground Mechanical | 6/26/2020 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 7/6/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Gas Test | 7/6/2020 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 7/6/2020 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 7/6/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 7/6/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Gas Test | 7/8/2020 | Approved | THOMAS FINNILA |
| Pre-Inspection | 7/8/2020 | Approved | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 7/8/2020 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 7/22/2020 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 7/22/2020 | Approved | THOMAS FINNILA |
| Wood Frame | 7/22/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Sewer | 7/30/2020 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2020 | Partial Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 10/15/2020 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 10/22/2020 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2020 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 10/22/2020 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 10/22/2020 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 11/10/2020 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 11/10/2020 | Approved | THOMAS FINNILA |
| HVAC-Rough | 11/10/2020 | Approved | THOMAS FINNILA |
| Drywall Nailing | 11/24/2020 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 5/21/2021 | Approved | THOMAS FINNILA |
| Final | 5/21/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 5/21/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Rough | 5/21/2021 | Approved | THOMAS FINNILA |
| MERV13>=Rough | 5/21/2021 | Approved | THOMAS FINNILA |
| Final | 10/14/2021 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 10/14/2021 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Final | 10/14/2021 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 10/14/2021 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 10/14/2021 | Approved | THOMAS FINNILA |
| Final | 10/26/2021 | OK to Issue CofO | ARAM AVEDISIAN |
| Green Building Final | 10/26/2021 | Approved | ARAM AVEDISIAN |