4835 W VENICE BLVD 90019
Certificate Information: 4835 W VENICE BLVD 90019
- Application / Permit
- 18016-20000-17321
- Plan Check / Job No.
- B18VN09231
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- REMOVE ENTIRE (E) BANK BUILDING EXCEPT FOR (8) EXISTING PILASTERS W/ FOOTINGS & ADD 2-STORY RESTAURANT; CHANGE OF USE FROM BANK TO RESTAURANT (NFPA-13 FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 2/7/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 6/14/2018 | APPLICANT |
| Green Plans Picked Up | 6/14/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2018 | NILOOFAR MEHRAIN |
| Corrections Issued | 6/25/2018 | NILOOFAR MEHRAIN |
| Quality Review Completed | 6/25/2018 | ABDUL CHEGENI |
| Building Plans Picked Up | 6/28/2018 | APPLICANT |
| Applicant returned to address corrections | 8/30/2018 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 9/14/2018 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 9/17/2018 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 9/28/2018 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 10/1/2018 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 10/17/2018 | NILOOFAR MEHRAIN |
| Plan Check Approved | 10/24/2018 | NILOOFAR MEHRAIN |
| Issued | 2/7/2019 | LADBS |
| CofO in Progress | 11/9/2021 | TIMOTHY BUXTON |
| CofO Issued | 11/19/2021 | ERNESTO CORRAL |
| Permit Finaled | 11/19/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 7/30/2018 | LEE GUILBEAUX |
| Comm Cor/Mini-Mall | Cleared | 7/30/2018 | DENNIS CHEW |
| Miscellaneous | Cleared | 7/30/2018 | DENNIS CHEW |
| Miscellaneous | Cleared | 7/30/2018 | DENNIS CHEW |
| ZA Case | Cleared | 7/30/2018 | DENNIS CHEW |
| ZI | Cleared | 7/30/2018 | DENNIS CHEW |
| Project located in CRA area | Cleared | 8/7/2018 | JIM URQUHART |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2018 | NAZILA NOORIFAR |
| Highway dedication | Cleared | 8/10/2018 | NAZILA NOORIFAR |
| Prkng lot landscape/Water mgmt | Cleared | 8/17/2018 | DENNIS CHEW |
| Hydrant and Access approval | Cleared | 9/12/2018 | GEORGE SUCHAND |
| Comm Cor/Mini-Mall | Cleared | 9/28/2018 | DENNIS CHEW |
| Fire Marshall Fire Life Safety | Cleared | 10/5/2018 | WILLIAM JOHNS |
| Green Code | Cleared | 10/15/2018 | DAVID MATSON |
| DAS Clearance | Cleared | 10/17/2018 | NILOOFAR MEHRAIN |
| Flood clearance | Cleared | 10/23/2018 | SYLVIA DHIMDIS |
| Food establishment approval | Cleared | 10/24/2018 | LACDHS APPROVED |
| Food Service Establishment | Cleared | 10/25/2018 | KENNETH BROWNE |
| ZA Case | Cleared | 10/29/2018 | CLAUDE GOODING |
| Low Impact Development | Cleared | 1/30/2019 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 1/30/2019 | JAMES MORALEZ |
| Stormwater Pollution Mitigatn | Cleared | 1/30/2019 | RYAN HUDSON |
| Sewer availability | Cleared | 2/5/2019 | JOHN LIN |
| Public Works-Highway Ded. | Cleared | 3/3/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Architect | Hatfield, Russell; Lic. No.: C22468 | 195 S 'C' STREET, SUITE 200 TUSTIN, CA 92780 |
| Contractor | Haraden Marshall Group Inc The; Lic. No.: 479705-B | 31127 VIA COLINAS SUITE 801 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Abernathy, Douglas Todd; Lic. No.: GE2547 | 7577 QUIET COVE CIR HUNTINGTON BEACH, CA 92648 |
| Engineer | Lascola, James Joseph; Lic. No.: S3149 | 26652 VUELTA RICA CAPISTRANO, CA 92624 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/1/2019 | Not Ready for Inspection | FELIX CEBALLOS |
| METHANE-Barrier | 5/1/2019 | Not Ready for Inspection | FELIX CEBALLOS |
| METHANE-Subgrade | 5/1/2019 | Not Ready for Inspection | FELIX CEBALLOS |
| Excavation/Setback/Form/Re-Bar | 6/21/2019 | No Access for Inspection | DAVID BURKHEAD |
| Footing/Foundation/Slab | 10/16/2019 | Partial Approval | FELIX CEBALLOS |
| METHANE-Barrier | 10/16/2019 | Partial Approval | FELIX CEBALLOS |
| METHANE-Subgrade | 10/16/2019 | Partial Approval | FELIX CEBALLOS |
| Deputy Reinf. Concrete | 10/21/2019 | Conditional Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 11/1/2019 | Partial Approval | TIMOTHY BUXTON |
| METHANE-Barrier | 11/1/2019 | Not Ready for Inspection | TIMOTHY BUXTON |
| METHANE-Subgrade | 11/1/2019 | Not Ready for Inspection | TIMOTHY BUXTON |
| Deputy Reinf. Concrete | 12/10/2019 | Conditional Approval | JONATHAN QUACH |
| Deputy Methane Barrier | 12/18/2019 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Methane Barrier | 12/19/2019 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Methane Barrier | 12/20/2019 | Conditional Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 12/20/2019 | Partial Approval | TIMOTHY BUXTON |
| METHANE-Barrier | 12/20/2019 | Partial Approval | TIMOTHY BUXTON |
| METHANE-Subgrade | 12/20/2019 | Partial Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 1/8/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Steel/Welding | 1/9/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Steel/Welding | 1/10/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Steel/Welding | 1/13/2020 | Conditional Approval | TIMOTHY BUXTON |
| Reinforced Concrete Frame | 1/13/2020 | Partial Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 1/14/2020 | Conditional Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 1/22/2020 | Partial Approval | TIMOTHY BUXTON |
| METHANE-Barrier | 1/22/2020 | Approved | TIMOTHY BUXTON |
| METHANE-Subgrade | 1/22/2020 | Approved | TIMOTHY BUXTON |
| Deputy Drilled-In Anchors | 1/24/2020 | Conditional Approval | JONATHAN QUACH |
| Footing/Foundation/Slab | 1/24/2020 | Approved | TIMOTHY BUXTON |
| Deputy Drilled-In Anchors | 2/5/2020 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Reinf. Concrete | 2/5/2020 | Conditional Approval | TIMOTHY BUXTON |
| Excavation/Setback/Form/Re-Bar | 2/7/2020 | Partial Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 2/14/2020 | Partial Approval | JONATHAN QUACH |
| Deputy Drilled-In Anchors | 2/18/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Methane Barrier | 2/18/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 2/18/2020 | Conditional Approval | JONATHAN QUACH |
| METHANE-Rough | 2/19/2020 | Not Ready for Inspection | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 2/24/2020 | Not Ready for Inspection | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 2/28/2020 | Partial Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 3/6/2020 | Approved | TIMOTHY BUXTON |
| Deputy Drilled-In Anchors | 3/17/2020 | Conditional Approval | JONATHAN QUACH |
| Masonry Wall/Backfill | 3/20/2020 | Partial Approval | TIMOTHY BUXTON |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2020 | Partial Approval | TIMOTHY BUXTON |
| Green Building Rough | 3/25/2020 | Approved | TIMOTHY BUXTON |
| METHANE-Rough | 3/25/2020 | Not Ready for Inspection | TIMOTHY BUXTON |
| Excavation/Setback/Form/Re-Bar | 3/31/2020 | Partial Approval | TIMOTHY BUXTON |
| Deputy Reinf. Concrete | 4/1/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Steel/Welding | 4/3/2020 | Corrections Issued | FELIX CEBALLOS |
| METHANE-Rough | 4/3/2020 | Approved | TIMOTHY BUXTON |
| Wood Frame | 4/3/2020 | Partial Approval | TIMOTHY BUXTON |
| Deputy Drilled-In Anchors | 4/8/2020 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 4/8/2020 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 4/14/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Steel/Welding | 4/15/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Steel/Welding | 4/16/2020 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 4/17/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Steel/Welding | 4/20/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Steel/Welding | 4/21/2020 | Conditional Approval | JONATHAN QUACH |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2020 | Partial Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 6/29/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Drilled-In Anchors | 7/1/2020 | Conditional Approval | JONATHAN QUACH |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2020 | Partial Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 7/6/2020 | Partial Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 7/8/2020 | Partial Approval | TIMOTHY BUXTON |
| Deputy Reinf. Concrete | 7/14/2020 | Conditional Approval | TIMOTHY BUXTON |
| Light Gage Steel Frame | 7/17/2020 | Partial Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 7/20/2020 | Conditional Approval | TIMOTHY BUXTON |
| Light Gage Steel Frame | 8/7/2020 | Partial Approval | TIMOTHY BUXTON |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2020 | Partial Approval | TIMOTHY BUXTON |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2020 | Partial Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 9/4/2020 | Partial Approval | TIMOTHY BUXTON |
| Light Gage Steel Frame | 9/16/2020 | Partial Approval | TIMOTHY BUXTON |
| Wood Frame | 9/24/2020 | Partial Approval | TIMOTHY BUXTON |
| Light Gage Steel Frame | 10/5/2020 | Partial Approval | TIMOTHY BUXTON |
| Insulation | 10/7/2020 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 10/14/2020 | Partial Approval | TIMOTHY BUXTON |
| Light Gage Steel Frame | 10/22/2020 | Corrections Issued | TIMOTHY BUXTON |
| Interior/Exterior Lathing | 12/14/2020 | Approved | TIMOTHY BUXTON |
| Interior/Exterior Lathing | 1/7/2021 | Partial Approval | TIMOTHY BUXTON |
| Light Gage Steel Frame | 1/11/2021 | Partial Approval | TIMOTHY BUXTON |
| Light Gage Steel Frame | 1/13/2021 | Partial Approval | TIMOTHY BUXTON |
| Drywall Nailing | 1/20/2021 | Approved | TIMOTHY BUXTON |
| Interior/Exterior Lathing | 1/20/2021 | Approved | TIMOTHY BUXTON |
| Light Gage Steel Frame | 1/20/2021 | Approved | TIMOTHY BUXTON |
| Deputy Steel/Welding | 1/21/2021 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 1/25/2021 | Conditional Approval | TIMOTHY BUXTON |
| T-Bar Ceiling | 4/19/2021 | Approved | TIMOTHY BUXTON |
| Final | 5/20/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Footing/Foundation/Slab | 5/20/2021 | Approved | DARRYL ARNOLD |
| Green Building Final | 5/20/2021 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 5/20/2021 | SGSOV Not Ready | DARRYL ARNOLD |
| SUSMP-Std. Urban Storm Water | 5/20/2021 | Approved | DARRYL ARNOLD |
| Smoke Detectors | 5/20/2021 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 5/20/2021 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 5/20/2021 | Conditional Approval | DARRYL ARNOLD |
| Final | 5/26/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 5/26/2021 | SGSOV Approved | TIMOTHY BUXTON |
| Smoke Detectors | 5/26/2021 | Approved | TIMOTHY BUXTON |
| Structural Steel Frame | 5/26/2021 | Approved | TIMOTHY BUXTON |
| Wood Frame | 5/26/2021 | Approved | TIMOTHY BUXTON |
| Pre-Inspection | 6/11/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Final | 6/25/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Final | 7/7/2021 | OK for TCO | TIMOTHY BUXTON |
| Final | 8/11/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Final | 8/20/2021 | Conditional Approval | TIMOTHY BUXTON |