4835 W VENICE BLVD 90019

Certificate Information: 4835 W VENICE BLVD 90019

Application / Permit
18016-20000-17321
Plan Check / Job No.
B18VN09231
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
REMOVE ENTIRE (E) BANK BUILDING EXCEPT FOR (8) EXISTING PILASTERS W/ FOOTINGS & ADD 2-STORY RESTAURANT; CHANGE OF USE FROM BANK TO RESTAURANT (NFPA-13 FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 2/7/2019
Issuing Office
Valley
Current Status
CofO Issued on 11/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2018 APPLICANT
Disabled Access Plans Picked Up 6/14/2018 APPLICANT
Green Plans Picked Up 6/14/2018 APPLICANT
Assigned to Plan Check Engineer 6/21/2018 NILOOFAR MEHRAIN
Corrections Issued 6/25/2018 NILOOFAR MEHRAIN
Quality Review Completed 6/25/2018 ABDUL CHEGENI
Building Plans Picked Up 6/28/2018 APPLICANT
Applicant returned to address corrections 8/30/2018 NILOOFAR MEHRAIN
Applicant returned to address corrections 9/14/2018 NILOOFAR MEHRAIN
Applicant returned to address corrections 9/17/2018 NILOOFAR MEHRAIN
Applicant returned to address corrections 9/28/2018 NILOOFAR MEHRAIN
Applicant returned to address corrections 10/1/2018 NILOOFAR MEHRAIN
Applicant returned to address corrections 10/17/2018 NILOOFAR MEHRAIN
Plan Check Approved 10/24/2018 NILOOFAR MEHRAIN
Issued 2/7/2019 LADBS
CofO in Progress 11/9/2021 TIMOTHY BUXTON
CofO Issued 11/19/2021 ERNESTO CORRAL
Permit Finaled 11/19/2021 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 7/30/2018 LEE GUILBEAUX
Comm Cor/Mini-Mall Cleared 7/30/2018 DENNIS CHEW
Miscellaneous Cleared 7/30/2018 DENNIS CHEW
Miscellaneous Cleared 7/30/2018 DENNIS CHEW
ZA Case Cleared 7/30/2018 DENNIS CHEW
ZI Cleared 7/30/2018 DENNIS CHEW
Project located in CRA area Cleared 8/7/2018 JIM URQUHART
Eng Process Fee Ord 176,300 Cleared 8/10/2018 NAZILA NOORIFAR
Highway dedication Cleared 8/10/2018 NAZILA NOORIFAR
Prkng lot landscape/Water mgmt Cleared 8/17/2018 DENNIS CHEW
Hydrant and Access approval Cleared 9/12/2018 GEORGE SUCHAND
Comm Cor/Mini-Mall Cleared 9/28/2018 DENNIS CHEW
Fire Marshall Fire Life Safety Cleared 10/5/2018 WILLIAM JOHNS
Green Code Cleared 10/15/2018 DAVID MATSON
DAS Clearance Cleared 10/17/2018 NILOOFAR MEHRAIN
Flood clearance Cleared 10/23/2018 SYLVIA DHIMDIS
Food establishment approval Cleared 10/24/2018 LACDHS APPROVED
Food Service Establishment Cleared 10/25/2018 KENNETH BROWNE
ZA Case Cleared 10/29/2018 CLAUDE GOODING
Low Impact Development Cleared 1/30/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 1/30/2019 JAMES MORALEZ
Stormwater Pollution Mitigatn Cleared 1/30/2019 RYAN HUDSON
Sewer availability Cleared 2/5/2019 JOHN LIN
Public Works-Highway Ded. Cleared 3/3/2020 JOHN TRIANTAFYLLOS

Contact Information

Architect Hatfield, Russell; Lic. No.: C22468 195 S 'C' STREET, SUITE 200      TUSTIN, CA 92780
Contractor Haraden Marshall Group Inc The; Lic. No.: 479705-B 31127 VIA COLINAS SUITE 801      WESTLAKE VILLAGE, CA 91362
Engineer Abernathy, Douglas Todd; Lic. No.: GE2547 7577 QUIET COVE CIR      HUNTINGTON BEACH, CA 92648
Engineer Lascola, James Joseph; Lic. No.: S3149 26652 VUELTA RICA      CAPISTRANO, CA 92624

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/1/2019 Not Ready for Inspection FELIX CEBALLOS
METHANE-Barrier 5/1/2019 Not Ready for Inspection FELIX CEBALLOS
METHANE-Subgrade 5/1/2019 Not Ready for Inspection FELIX CEBALLOS
Excavation/Setback/Form/Re-Bar 6/21/2019 No Access for Inspection DAVID BURKHEAD
Footing/Foundation/Slab 10/16/2019 Partial Approval FELIX CEBALLOS
METHANE-Barrier 10/16/2019 Partial Approval FELIX CEBALLOS
METHANE-Subgrade 10/16/2019 Partial Approval FELIX CEBALLOS
Deputy Reinf. Concrete 10/21/2019 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 11/1/2019 Partial Approval TIMOTHY BUXTON
METHANE-Barrier 11/1/2019 Not Ready for Inspection TIMOTHY BUXTON
METHANE-Subgrade 11/1/2019 Not Ready for Inspection TIMOTHY BUXTON
Deputy Reinf. Concrete 12/10/2019 Conditional Approval JONATHAN QUACH
Deputy Methane Barrier 12/18/2019 Conditional Approval TIMOTHY BUXTON
Deputy Methane Barrier 12/19/2019 Conditional Approval TIMOTHY BUXTON
Deputy Methane Barrier 12/20/2019 Conditional Approval TIMOTHY BUXTON
Footing/Foundation/Slab 12/20/2019 Partial Approval TIMOTHY BUXTON
METHANE-Barrier 12/20/2019 Partial Approval TIMOTHY BUXTON
METHANE-Subgrade 12/20/2019 Partial Approval TIMOTHY BUXTON
Deputy Steel/Welding 1/8/2020 Conditional Approval JONATHAN QUACH
Deputy Steel/Welding 1/9/2020 Conditional Approval JONATHAN QUACH
Deputy Steel/Welding 1/10/2020 Conditional Approval JONATHAN QUACH
Deputy Steel/Welding 1/13/2020 Conditional Approval TIMOTHY BUXTON
Reinforced Concrete Frame 1/13/2020 Partial Approval TIMOTHY BUXTON
Deputy Steel/Welding 1/14/2020 Conditional Approval TIMOTHY BUXTON
Footing/Foundation/Slab 1/22/2020 Partial Approval TIMOTHY BUXTON
METHANE-Barrier 1/22/2020 Approved TIMOTHY BUXTON
METHANE-Subgrade 1/22/2020 Approved TIMOTHY BUXTON
Deputy Drilled-In Anchors 1/24/2020 Conditional Approval JONATHAN QUACH
Footing/Foundation/Slab 1/24/2020 Approved TIMOTHY BUXTON
Deputy Drilled-In Anchors 2/5/2020 Conditional Approval TIMOTHY BUXTON
Deputy Reinf. Concrete 2/5/2020 Conditional Approval TIMOTHY BUXTON
Excavation/Setback/Form/Re-Bar 2/7/2020 Partial Approval TIMOTHY BUXTON
Footing/Foundation/Slab 2/14/2020 Partial Approval JONATHAN QUACH
Deputy Drilled-In Anchors 2/18/2020 Conditional Approval JONATHAN QUACH
Deputy Methane Barrier 2/18/2020 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 2/18/2020 Conditional Approval JONATHAN QUACH
METHANE-Rough 2/19/2020 Not Ready for Inspection TIMOTHY BUXTON
Footing/Foundation/Slab 2/24/2020 Not Ready for Inspection TIMOTHY BUXTON
Footing/Foundation/Slab 2/28/2020 Partial Approval TIMOTHY BUXTON
Footing/Foundation/Slab 3/6/2020 Approved TIMOTHY BUXTON
Deputy Drilled-In Anchors 3/17/2020 Conditional Approval JONATHAN QUACH
Masonry Wall/Backfill 3/20/2020 Partial Approval TIMOTHY BUXTON
Floor/Roof Diaphrgm/Shear Wall 3/25/2020 Partial Approval TIMOTHY BUXTON
Green Building Rough 3/25/2020 Approved TIMOTHY BUXTON
METHANE-Rough 3/25/2020 Not Ready for Inspection TIMOTHY BUXTON
Excavation/Setback/Form/Re-Bar 3/31/2020 Partial Approval TIMOTHY BUXTON
Deputy Reinf. Concrete 4/1/2020 Conditional Approval JONATHAN QUACH
Deputy Steel/Welding 4/3/2020 Corrections Issued FELIX CEBALLOS
METHANE-Rough 4/3/2020 Approved TIMOTHY BUXTON
Wood Frame 4/3/2020 Partial Approval TIMOTHY BUXTON
Deputy Drilled-In Anchors 4/8/2020 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 4/8/2020 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 4/14/2020 Conditional Approval JONATHAN QUACH
Deputy Steel/Welding 4/15/2020 Conditional Approval JONATHAN QUACH
Deputy Steel/Welding 4/16/2020 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 4/17/2020 Conditional Approval JONATHAN QUACH
Deputy Steel/Welding 4/20/2020 Conditional Approval JONATHAN QUACH
Deputy Steel/Welding 4/21/2020 Conditional Approval JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 4/22/2020 Partial Approval TIMOTHY BUXTON
Deputy Steel/Welding 6/29/2020 Conditional Approval JONATHAN QUACH
Deputy Drilled-In Anchors 7/1/2020 Conditional Approval JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 7/2/2020 Partial Approval TIMOTHY BUXTON
Footing/Foundation/Slab 7/6/2020 Partial Approval TIMOTHY BUXTON
Footing/Foundation/Slab 7/8/2020 Partial Approval TIMOTHY BUXTON
Deputy Reinf. Concrete 7/14/2020 Conditional Approval TIMOTHY BUXTON
Light Gage Steel Frame 7/17/2020 Partial Approval TIMOTHY BUXTON
Deputy Steel/Welding 7/20/2020 Conditional Approval TIMOTHY BUXTON
Light Gage Steel Frame 8/7/2020 Partial Approval TIMOTHY BUXTON
Floor/Roof Diaphrgm/Shear Wall 8/12/2020 Partial Approval TIMOTHY BUXTON
Floor/Roof Diaphrgm/Shear Wall 8/21/2020 Partial Approval TIMOTHY BUXTON
Footing/Foundation/Slab 9/4/2020 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 9/16/2020 Partial Approval TIMOTHY BUXTON
Wood Frame 9/24/2020 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 10/5/2020 Partial Approval TIMOTHY BUXTON
Insulation 10/7/2020 Approved TIMOTHY BUXTON
Drywall Nailing 10/14/2020 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 10/22/2020 Corrections Issued TIMOTHY BUXTON
Interior/Exterior Lathing 12/14/2020 Approved TIMOTHY BUXTON
Interior/Exterior Lathing 1/7/2021 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 1/11/2021 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 1/13/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 1/20/2021 Approved TIMOTHY BUXTON
Interior/Exterior Lathing 1/20/2021 Approved TIMOTHY BUXTON
Light Gage Steel Frame 1/20/2021 Approved TIMOTHY BUXTON
Deputy Steel/Welding 1/21/2021 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 1/25/2021 Conditional Approval TIMOTHY BUXTON
T-Bar Ceiling 4/19/2021 Approved TIMOTHY BUXTON
Final 5/20/2021 Not Ready for Inspection DARRYL ARNOLD
Footing/Foundation/Slab 5/20/2021 Approved DARRYL ARNOLD
Green Building Final 5/20/2021 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 5/20/2021 SGSOV Not Ready DARRYL ARNOLD
SUSMP-Std. Urban Storm Water 5/20/2021 Approved DARRYL ARNOLD
Smoke Detectors 5/20/2021 Conditional Approval DARRYL ARNOLD
Structural Steel Frame 5/20/2021 Conditional Approval DARRYL ARNOLD
Wood Frame 5/20/2021 Conditional Approval DARRYL ARNOLD
Final 5/26/2021 Not Ready for Inspection TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 5/26/2021 SGSOV Approved TIMOTHY BUXTON
Smoke Detectors 5/26/2021 Approved TIMOTHY BUXTON
Structural Steel Frame 5/26/2021 Approved TIMOTHY BUXTON
Wood Frame 5/26/2021 Approved TIMOTHY BUXTON
Pre-Inspection 6/11/2021 Not Ready for Inspection TIMOTHY BUXTON
Final 6/25/2021 Not Ready for Inspection TIMOTHY BUXTON
Final 7/7/2021 OK for TCO TIMOTHY BUXTON
Final 8/11/2021 Not Ready for Inspection TIMOTHY BUXTON
Final 8/20/2021 Conditional Approval TIMOTHY BUXTON