1913 S HILLSBORO AVE 90035

Certificate Information: 1913 S HILLSBORO AVE 90035

Application / Permit
18016-20000-17305
Plan Check / Job No.
B18VN09216
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ENCLOSE PATIO COVER AND GARAGE CONVERT TO ACCESSORY DWELLING UNIT PER AB494 AND SB229.
Permit Issued
Issued on 3/29/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2018 APPLICANT
Assigned to Plan Check Engineer 6/21/2018 SARAH YOUSSEF
Corrections Issued 6/23/2018 SARAH YOUSSEF
Quality Review Completed 6/25/2018 STEVEN KIM
Building Plans Picked Up 6/26/2018 APPLICANT
Applicant returned to address corrections 2/25/2019 ABDUL CHEGENI
Plan Check Approved 3/20/2019 ABDUL CHEGENI
Issued 3/29/2019 LADBS
CofO in Progress 6/1/2023 CLAYTON GRAHAM
Permit Finaled 6/8/2023 DANIEL ORRANTE
CofO Issued 6/8/2023 DANIEL ORRANTE
Permit Finaled 6/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/24/2018 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 10/24/2018 APEKSHYA BAJRACHARYA
Sewer availability Cleared 10/24/2018 APEKSHYA BAJRACHARYA
Construction near power lines Cleared 1/26/2019 RIDWAN HARDY
Grading Pre-Inspection Cleared 2/25/2019 SARAH YOUSSEF

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/21/2020 Partial Inspection KEVIN SARGSYAN
Deputy Drilled-In Anchors 1/27/2021 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 2/3/2021 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 4/15/2021 Partial Approval KEVIN SARGSYAN
Sewer 4/15/2021 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 4/30/2021 Corrections Issued EVAN COOPER
Sewer 4/30/2021 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 5/17/2021 Not Ready for Inspection KEVIN SARGSYAN
Sewer 5/17/2021 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 5/21/2021 Corrections Issued KEVIN SARGSYAN
Sewer 5/21/2021 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 5/26/2021 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 5/26/2021 Partial Approval KEVIN SARGSYAN
Sewer 5/26/2021 Approved KEVIN SARGSYAN
Pre-Inspection 8/17/2021 Partial Inspection KEVIN SARGSYAN
Pre-Inspection 10/15/2021 Partial Inspection KEVIN SARGSYAN
Underground Mechanical 10/15/2021 Partial Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 2/10/2022 Corrections Issued EVAN COOPER
PLUMBING-Rough 2/10/2022 Corrections Issued EVAN COOPER
PLUMBING-Rough 2/14/2022 No Access for Inspection KEVIN SARGSYAN
PLUMBING-Rough 2/16/2022 Partial Approval BRENDAN LOONEY
Wood Frame 4/4/2022 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 7/19/2022 Partial Approval STEPHANIE SWANSON
Gas Test 7/19/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 8/2/2022 Corrections Issued EVAN COOPER
Interior/Exterior Lathing 8/2/2022 Partial Approval EVAN COOPER
Wood Frame 8/15/2022 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Rough 8/24/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 8/24/2022 Approved OGANES TARAKHCHYAN
HVAC-Rough 9/9/2022 Approved OGANES TARAKHCHYAN
Wood Frame 9/9/2022 Approved OGANES TARAKHCHYAN
Insulation 9/20/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Insulation 9/26/2022 Approved OGANES TARAKHCHYAN
Drywall Nailing 10/4/2022 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/19/2022 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 11/21/2022 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 12/1/2022 Approved EVAN COOPER
METHANE-Final 12/1/2022 Approved EVAN COOPER
METHANE-Rough 12/1/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/1/2022 SGSOV Not Ready EVAN COOPER
Service/Power Release 12/1/2022 Corrections Issued EVAN COOPER
Smoke Detectors 12/1/2022 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Final 2/3/2023 Corrections Issued ASHLEY THOMPSON
Final 2/3/2023 Corrections Issued ASHLEY THOMPSON
HVAC-Final 2/3/2023 Corrections Issued ASHLEY THOMPSON
PLUMBING-Final 2/3/2023 Corrections Issued ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 2/3/2023 SGSOV Not Ready ASHLEY THOMPSON
Smoke Detectors 2/3/2023 Approved ASHLEY THOMPSON
Final 5/10/2023 Corrections Issued CLAYTON GRAHAM
PLUMBING-Final 5/10/2023 Approved CLAYTON GRAHAM
SGSOV-Seismic Gas S/O Valve 5/10/2023 SGSOV Not Ready CLAYTON GRAHAM
Final 5/22/2023 Corrections Issued CLAYTON GRAHAM
SGSOV-Seismic Gas S/O Valve 5/22/2023 SGSOV Not Ready CLAYTON GRAHAM
ELECTRICAL-Final 5/31/2023 Approved CLAYTON GRAHAM
Final 5/31/2023 OK to Issue CofO CLAYTON GRAHAM
HVAC-Final 5/31/2023 Approved CLAYTON GRAHAM
SGSOV-Seismic Gas S/O Valve 5/31/2023 SGSOV Approved CLAYTON GRAHAM
Service/Power Release 5/31/2023 Approved CLAYTON GRAHAM