14061 W VANOWEN ST 91405

Certificate Information: 14061 W VANOWEN ST 91405

Application / Permit
18016-20000-16768
Plan Check / Job No.
B18VN08940
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Medical Office
Work Description
CHANGE OF USE FROM RETAIL TO MEDICAL OFFICE
Permit Issued
Issued on 1/14/2019
Issuing Office
Valley
Current Status
CofO Issued on 9/23/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2018 APPLICANT
Disabled Access Plans Picked Up 6/8/2018 APPLICANT
Assigned to Plan Check Engineer 6/14/2018 CHON CHIO KUO
Corrections Issued 6/18/2018 CHON CHIO KUO
Quality Review Completed 6/19/2018 STEVEN KIM
Building Plans Picked Up 6/22/2018 APPLICANT
Applicant returned to address corrections 12/27/2018 CHON CHIO KUO
Plan Check Approved 1/14/2019 CHON CHIO KUO
Issued 1/14/2019 LADBS
TCO Issued (Expire Date: 08-19-2020) 2/21/2020 JAMES STEPHENS
CofO in Progress 9/23/2020 JEFFREY DURAN
Permit Finaled 9/23/2020 JEFFREY DURAN
CofO Issued 9/23/2020 JEFFREY DURAN
Permit Finaled 9/23/2020 JEFFREY DURAN

Permit Application Clearance Information

DAS Clearance Cleared 9/12/2018 CHON CHIO KUO
"Q" conditions Cleared 12/27/2018 DAISY BENICIA
Eng Process Fee Ord 176,300 Cleared 12/27/2018 RUDY TERRIQUEZ.
Prkng lot landscape/Water mgmt Cleared 12/27/2018 DAISY BENICIA
Sewer availability Cleared 12/27/2018 RUDY TERRIQUEZ.
ZA Case Cleared 12/27/2018 DAISY BENICIA
ZA Case Cleared 12/27/2018 DAISY BENICIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SEAN GRIFFITH, (818) 374-1102 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 5/17/2019 Corrections Issued CAMERON CHABAN
Light Gage Steel Frame 5/23/2019 Approved CAMERON CHABAN
Drywall Nailing 6/10/2019 Approved ANDREW DORSO
Pre-Inspection 6/10/2019 Corrections Issued ANDREW DORSO
Final 1/3/2020 Partial Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 1/3/2020 SGSOV Not Ready CAMERON CHABAN
Smoke Detectors 1/3/2020 Corrections Issued CAMERON CHABAN
Wood Frame 1/3/2020 Approved CAMERON CHABAN
Final 1/23/2020 Corrections Issued ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 1/23/2020 SGSOV Not Ready ANDREW DORSO
Smoke Detectors 1/23/2020 Not Ready for Inspection ANDREW DORSO
Final 2/7/2020 Corrections Issued GARY EWELL
SGSOV-Seismic Gas S/O Valve 2/7/2020 SGSOV Not Ready GARY EWELL
Smoke Detectors 2/7/2020 Conditional Approval GARY EWELL
Final 2/19/2020 Conditional Approval GARY EWELL
SGSOV-Seismic Gas S/O Valve 2/19/2020 SGSOV Approved GARY EWELL
Smoke Detectors 2/19/2020 Approved GARY EWELL
Special/Order Compliance 2/20/2020 Partial Inspection JAMES STEPHENS
Special/Order Compliance 8/6/2020 Partial Inspection ANDREW DORSO
Final 9/23/2020 OK to Issue CofO JEFFREY DURAN