6335 N BABCOCK AVE 91606
Certificate Information: 6335 N BABCOCK AVE 91606
- Application / Permit
- 18016-20000-16696
- Plan Check / Job No.
- B18VN08900
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) (17' X 19'-1") DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 3/2/2021
- Issuing Office
- Current Status
- Issued on 3/2/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/25/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2018 | RAPHAEL ROSAS |
| Corrections Issued | 5/25/2018 | RAPHAEL ROSAS |
| Issued | 3/2/2021 | APPLICANT |
| Building Plans Picked Up | 3/2/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/30/2018 | KENNETH PHAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/30/2018 | KENNETH PHAM |
| Roof/Waste drainage to street | Cleared | 5/30/2018 | KENNETH PHAM |
| Sewer availability | Cleared | 5/30/2018 | KENNETH PHAM |
| Construction near power lines | Cleared | 9/20/2018 | OSCAR CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 10/18/2022 | Corrections Issued | WILLIAM WREN |
| Pre-Inspection | 10/19/2022 | No Access for Inspection | WILLIAM WREN |
| Sewer | 10/19/2022 | No Access for Inspection | WILLIAM WREN |
| Footing/Foundation/Slab | 11/17/2022 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 11/17/2022 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 11/28/2022 | Corrections Issued | KIRK SANDERS |
| Underground Mechanical | 11/28/2022 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 1/4/2023 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 1/4/2023 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 1/4/2023 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 1/4/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 1/4/2023 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 1/10/2023 | Conditional Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 1/10/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 1/10/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 1/10/2023 | Approved | KIRK SANDERS |
| Insulation | 1/12/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 1/17/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/21/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 3/21/2023 | Corrections Issued | KIRK SANDERS |
| Final | 3/21/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 3/21/2023 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 3/21/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 3/21/2023 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 3/21/2023 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 3/21/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 6/7/2023 | Corrections Issued | KIRK SANDERS |
| Final | 6/7/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 6/7/2023 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 6/7/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 6/7/2023 | Approved | KIRK SANDERS |
| Final | 4/10/2025 | No Access for Inspection | GAREN HAYRAPETYAN |
| Green Building Final | 4/10/2025 | No Access for Inspection | GAREN HAYRAPETYAN |
| Final | 5/19/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 6/6/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 6/11/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 6/11/2025 | Approved | GAREN HAYRAPETYAN |