5919 N RHODES AVE 91607

Certificate Information: 5919 N RHODES AVE 91607

Application / Permit
18016-20000-16128
Plan Check / Job No.
B18VN08549
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE/RECREATION ROOM BUILDING (1976VN39984) TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 292. ALL WORKS ARE PER WFPP.
Permit Issued
Issued on 9/14/2018
Issuing Office
Valley
Current Status
CofO Issued on 11/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2018 APPLICANT
Assigned to Plan Check Engineer 5/21/2018 ALDOUS CHIC
Corrections Issued 5/22/2018 ALDOUS CHIC
Building Plans Picked Up 5/29/2018 APPLICANT
Plan Check Approved 8/14/2018 ALDOUS CHIC
Issued 9/14/2018 LADBS
CofO in Progress 1/12/2021 MATTHEW NELSON
CofO Issued 11/13/2021 MICHAEL SMITH
Permit Finaled 11/13/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/9/2018 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 7/9/2018 JOHN LIN
Sewer availability Cleared 7/9/2018 JOHN LIN

Contact Information

Contractor Anderson Robert Construction; Lic. No.: 861662-B 18169 KNOLL HILL      GRANADA HILLS, CA 91344

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/14/2019 Not Ready for Inspection GREG ALLTON
Pre-Inspection 5/8/2019 Partial Inspection GREG ALLTON
Pre-Inspection 7/26/2019 Approved BEAU COLLINS
BUILDING-Rough-Frame 7/28/2020 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 7/28/2020 Approved BRENDAN LOONEY
Footing/Foundation/Slab 7/28/2020 Partial Approval BRENDAN LOONEY
HVAC-Rough 7/28/2020 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 7/28/2020 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 8/14/2020 Approved BRENDAN LOONEY
Green Building Rough 8/14/2020 Corrections Issued BRENDAN LOONEY
Rough-Elec/Plmb/HVAC 8/14/2020 Approved BRENDAN LOONEY
Insulation 8/27/2020 Approved BRENDAN LOONEY
Interior/Exterior Lathing 8/27/2020 Approved BRENDAN LOONEY
Drywall Nailing 9/8/2020 Approved ARAM AVEDISIAN
Gas Test 9/8/2020 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 12/17/2020 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Final 12/17/2020 Not Ready for Inspection BRENDAN LOONEY
Final 12/17/2020 Corrections Issued BRENDAN LOONEY
Green Building Final 12/17/2020 Not Ready for Inspection BRENDAN LOONEY
Green Building Rough 12/17/2020 Not Ready for Inspection BRENDAN LOONEY
HVAC-Final 12/17/2020 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Final 12/17/2020 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 12/17/2020 SGSOV Not Ready BRENDAN LOONEY
Service/Power Release 12/17/2020 Not Ready for Inspection BRENDAN LOONEY
Smoke Detectors 12/17/2020 Not Ready for Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 1/11/2021 Approved MATTHEW NELSON
ELECTRICAL-Final 1/11/2021 Approved MATTHEW NELSON
Final 1/11/2021 OK to Issue CofO MATTHEW NELSON
Green Building Final 1/11/2021 Approved MATTHEW NELSON
Green Building Rough 1/11/2021 Approved MATTHEW NELSON
HVAC-Final 1/11/2021 Approved MATTHEW NELSON
PLUMBING-Final 1/11/2021 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 1/11/2021 SGSOV Approved MATTHEW NELSON
Smoke Detectors 1/11/2021 Approved MATTHEW NELSON