10061 N VENA AVE 91331

Certificate Information: 10061 N VENA AVE 91331

Application / Permit
18016-20000-12376
Plan Check / Job No.
B18VN06739
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE EXISTING 24'X20' 2-STORY RECREATION ROOM/GARAGE INTO AN ACCESSORY DWELLING UNITS PER AB 494 AND SB 229. **"COMPLY WITH DEPARTMENT ORDER effective date 04/03/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 5/11/2018
Issuing Office
Valley
Current Status
CofO Issued on 1/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2018 APPLICANT
Assigned to Plan Check Engineer 4/23/2018 JOHNNY WU
Corrections Issued 4/23/2018 JOHNNY WU
Plan Check Approved 5/11/2018 ANGELICA MARTINEZ
Issued 5/11/2018 LADBS
CofO in Progress 1/19/2021 MICKEY YAMASHITA
CofO Issued 1/19/2021 DAVID JAMES
Permit Finaled 1/19/2021 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 4/23/2018 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/23/2018 LEE GUILBEAUX
Sewer availability Cleared 4/23/2018 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/23/2018 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/29/2019 Corrections Issued MICKEY YAMASHITA
Green Building Rough 2/20/2020 Corrections Issued MICKEY YAMASHITA
Pre-Inspection 2/20/2020 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 7/29/2020 Corrections Issued MICKEY YAMASHITA
Floor/Roof Diaphrgm/Shear Wall 8/19/2020 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 8/19/2020 Approved MICKEY YAMASHITA
Footing/Foundation/Slab 9/11/2020 Not Ready for Inspection THOMAS WOODS
Floor/Roof Diaphrgm/Shear Wall 9/22/2020 Approved MICKEY YAMASHITA
Wood Frame 10/7/2020 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 12/1/2020 Approved THOMAS WOODS
Insulation 12/1/2020 Approved THOMAS WOODS
Final 12/18/2020 Not Ready for Inspection THOMAS WOODS
Footing/Foundation/Slab 12/18/2020 Approved THOMAS WOODS
Green Building Final 12/18/2020 Not Ready for Inspection THOMAS WOODS
Green Building Rough 12/18/2020 Approved THOMAS WOODS
METHANE-Final 12/18/2020 Not Ready for Inspection THOMAS WOODS
METHANE-Rough 12/18/2020 Not Ready for Inspection THOMAS WOODS
SGSOV-Seismic Gas S/O Valve 12/18/2020 SGSOV Approved THOMAS WOODS
Smoke Detectors 12/18/2020 Partial Approval THOMAS WOODS
Wood Frame 12/18/2020 Partial Approval THOMAS WOODS
Floor/Roof Diaphrgm/Shear Wall 12/23/2020 Approved MICKEY YAMASHITA
Green Building Rough 12/23/2020 Approved MICKEY YAMASHITA
METHANE-Final 12/23/2020 Approved MICKEY YAMASHITA
METHANE-Rough 12/23/2020 Approved MICKEY YAMASHITA
Smoke Detectors 12/23/2020 Corrections Issued MICKEY YAMASHITA
Wood Frame 12/23/2020 Corrections Issued MICKEY YAMASHITA
Final 1/14/2021 OK to Issue CofO MICKEY YAMASHITA
Green Building Final 1/14/2021 Approved MICKEY YAMASHITA
Smoke Detectors 1/14/2021 Approved MICKEY YAMASHITA
Wood Frame 1/14/2021 Approved MICKEY YAMASHITA