5451 N BURNET AVE 91411

Certificate Information: 5451 N BURNET AVE 91411

Application / Permit
18016-20000-10390
Plan Check / Job No.
B18VN05677
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE 4'X12'-11" LIVING ROOM EXTENSION, DEMO ONE EXISTING WALL AT KITCHEN AND REMODEL KITCHEN.
Permit Issued
Issued on 4/5/2018
Issuing Office
Valley
Current Status
Issued on 4/5/2018
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/5/2018 APPLICANT
Assigned to Plan Check Engineer 4/5/2018 DAWN MC NULTY
Plan Check Approved 4/5/2018 DAWN MC NULTY
Issued 4/5/2018 LADBS

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Nguyen, Tuan Minh; Lic. No.: S5883 503 E FRANKLIN AVE 2      EL SEGUNDO, CA 90245

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 4/27/2022 Partial Inspection MICHAEL SMITH
Footing/Foundation/Slab 11/18/2022 Conditional Approval THOMAS FINNILA
METHANE-Barrier 11/18/2022 Conditional Approval THOMAS FINNILA
METHANE-Subgrade 11/18/2022 Approved THOMAS FINNILA
Pre-Inspection 12/1/2022 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/9/2022 Corrections Issued JACK KARGODORIAN
Green Building Rough 12/9/2022 Not Ready for Inspection JACK KARGODORIAN
METHANE-Rough 12/9/2022 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 2/21/2023 Not Ready for Inspection DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 2/21/2023 Approved DAVID MATSON
Green Building Rough 2/21/2023 Not Ready for Inspection DAVID MATSON
Interior/Exterior Lathing 2/28/2023 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 6/1/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 6/1/2023 Approved RYAN SALAZAR
Green Building Rough 6/1/2023 Approved RYAN SALAZAR
HVAC-Rough 6/1/2023 Approved RYAN SALAZAR
PLUMBING-Rough 6/1/2023 Approved RYAN SALAZAR
Insulation 6/7/2023 Approved THOMAS FINNILA
Drywall Nailing 6/14/2023 Approved THOMAS FINNILA