223-223 1/2 E 116TH ST 90061
Certificate Information: 223-223 1/2 E 116TH ST 90061
- Application / Permit
- 18016-20000-06269
- Plan Check / Job No.
- B18VN03463
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Convert (E) storage and garage on ground floor of existing 2 story SFD to UDU (22'-10" x32'-7") per ADM 2018-2803- UDU ordinance #184,907. Enclose 4'x22'-10" overhang for (N) bathroom and storage area. COMPLY WITH DEPARTMENT ORDER effective date 08/24/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 2/28/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2018 | APPLICANT |
| Green Plans Picked Up | 3/19/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2018 | ALYSSA N NARCISO |
| Corrections Issued | 4/6/2018 | ALYSSA N NARCISO |
| Quality Review Completed | 4/16/2018 | STEVEN KIM |
| Building Plans Picked Up | 4/17/2018 | APPLICANT |
| Applicant returned to address corrections | 10/25/2019 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 11/15/2019 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 1/9/2020 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 1/28/2020 | ALYSSA N NARCISO |
| Plan Check Approved | 2/27/2020 | ALYSSA N NARCISO |
| Plan Check Approved | 2/28/2020 | ALYSSA N NARCISO |
| Issued | 2/28/2020 | LADBS |
| CofO in Progress | 6/24/2022 | ALIZAH MAYAGOITIA |
| Permit Finaled | 4/24/2023 | DANIEL ORRANTE |
| CofO Issued | 4/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Green Code | Cleared | 5/15/2018 | SARKIS HARABEDIAN |
| Address approval | Cleared | 10/25/2018 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2018 | CELINA MORENO |
| Sewer availability | Cleared | 11/2/2018 | CELINA MORENO |
| Density Bonus 14.00.A.10 | Cleared | 5/21/2019 | KENNETH LE |
| Unpermitted Dwelling Unit | Cleared | 7/3/2019 | ULISES GONZALEZ |
| Density Bonus 12.22.A.25 | Cleared | 11/4/2019 | KENNETH LE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Segovia,, Felipe; Lic. No.: C41102 | 2320 SANTA CRUZ CT TORRANCE, CA 90501 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/8/2021 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 9/8/2021 | Partial Approval | EUGENE CASSIDY |
| Sewer | 9/8/2021 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 9/14/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/6/2021 | Approved | EUGENE CASSIDY |
| Deputy Wood Construction | 10/6/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/6/2021 | Conditional Approval | EUGENE CASSIDY |
| Green Building Rough | 10/6/2021 | Approved | EUGENE CASSIDY |
| MERV13>=Rough | 10/6/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 10/6/2021 | Approved | EUGENE CASSIDY |
| Insulation | 10/12/2021 | Corrections Issued | EUGENE CASSIDY |
| Drywall Nailing | 10/21/2021 | Corrections Issued | EUGENE CASSIDY |
| Drywall Nailing | 11/2/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 11/2/2021 | Partial Approval | EUGENE CASSIDY |
| Interior/Exterior Lathing | 11/4/2021 | Approved | EUGENE CASSIDY |
| Final | 4/20/2022 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 4/20/2022 | Corrections Issued | JOHN KLARIN |
| MERV13>=Final | 4/20/2022 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 4/20/2022 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 4/20/2022 | Corrections Issued | JOHN KLARIN |
| Final | 5/4/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| Green Building Final | 5/4/2022 | Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 5/4/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 5/5/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| Final | 5/25/2022 | Not Ready for Inspection | DONALD CRICHLOW |
| Final | 5/27/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 6/24/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 6/24/2022 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| HVAC-Final | 6/24/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 6/24/2022 | Approved | ALIZAH MAYAGOITIA |