349 N EDINBURGH AVE 90048

Certificate Information: 349 N EDINBURGH AVE 90048

Application / Permit
18016-20000-06149
Plan Check / Job No.
B18VN03402
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEER
Permit Issued
Issued on 3/23/2021
Issuing Office
Current Status
CofO Issued on 12/28/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2018 APPLICANT
Assigned to Plan Check Engineer 2/28/2018 JOSE MENDOZA
Corrections Issued 2/28/2018 SARAH YOUSSEF
Applicant returned to address corrections 7/25/2018 MARVEL DELACRUZ
Plan Check Approved 7/25/2018 JEROME MAGAT PALMA
Issued 3/23/2021 APPLICANT
Building Plans Picked Up 3/23/2021 APPLICANT
CofO in Progress 11/19/2021 CHRIS CHRISTENSEN
Permit Finaled 12/28/2021 RONALD MYRICK
CofO Issued 12/28/2021 RONALD MYRICK
Permit Finaled 12/28/2021 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 3/1/2018 KAYLA PEJI
CPC Cleared 3/1/2018 DAISY BENICIA
Sewer availability Cleared 3/1/2018 KAYLA PEJI
Construction within easement Cleared 7/10/2018 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 7/25/2018 KENNETH PHAM

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/16/2021 Corrections Issued CHRIS CHRISTENSEN
ELECTRICAL-Final 11/3/2021 Approved CHRIS CHRISTENSEN
Final 11/3/2021 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 11/3/2021 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 11/3/2021 Approved CHRIS CHRISTENSEN
METHANE-Final 11/3/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 11/3/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/3/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 11/3/2021 Approved CHRIS CHRISTENSEN
Final 11/18/2021 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 11/18/2021 Approved CHRIS CHRISTENSEN