9859 N GULLO AVE 91331

Certificate Information: 9859 N GULLO AVE 91331

Application / Permit
18016-20000-04737
Plan Check / Job No.
B18VN02605
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE EXIST. 18' x 20' DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER AB 494 & SB 229.
Permit Issued
Issued on 2/21/2018
Issuing Office
Valley
Current Status
Issued on 2/21/2018
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/14/2018 APPLICANT
Assigned to Plan Check Engineer 2/14/2018 ANDRES MATA
Corrections Issued 2/14/2018 ANDRES MATA
Issued 2/21/2018 LADBS

Permit Application Clearance Information

Address approval Cleared 2/14/2018 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/14/2018 LEE GUILBEAUX
Sewer availability Cleared 2/14/2018 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/27/2018 No Access for Inspection MICHEL ABAJAN
Green Building Rough 4/27/2018 No Access for Inspection MICHEL ABAJAN
METHANE-Rough 4/27/2018 No Access for Inspection MICHEL ABAJAN
PLUMBING-Rough 4/27/2018 No Access for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 4/30/2018 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 5/7/2018 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 5/16/2018 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 5/16/2018 Approved MICHEL ABAJAN
Green Building Rough 5/16/2018 Approved MICHEL ABAJAN
METHANE-Rough 5/16/2018 Approved MICHEL ABAJAN
Insulation 5/23/2018 Not Ready for Inspection MICHEL ABAJAN
Underground Mechanical 5/23/2018 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 5/30/2018 Approved MICHEL ABAJAN
PLUMBING-Final 5/30/2018 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 6/6/2018 Partial Approval MICHEL ABAJAN
Insulation 6/6/2018 Approved MICHEL ABAJAN
Interior/Exterior Lathing 6/6/2018 Approved MICHEL ABAJAN
Drywall Nailing 6/14/2018 Approved MICHEL ABAJAN
Interior/Exterior Lathing 6/14/2018 Approved MICHEL ABAJAN
ELECTRICAL-Rough 1/24/2019 No Access for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 1/25/2019 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 1/30/2019 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 6/7/2019 Partial Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 8/22/2019 Approved JENNIFER RABUCHIN
Special/Order Compliance 5/6/2020 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 5/18/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/18/2020 Corrections Issued JENNIFER RABUCHIN
Final 5/18/2020 Corrections Issued JENNIFER RABUCHIN
Green Building Final 5/18/2020 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 5/18/2020 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Final 5/18/2020 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/18/2020 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 5/18/2020 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 8/17/2020 Corrections Issued MICHEL ABAJAN
Final 8/17/2020 Corrections Issued MICHEL ABAJAN
Green Building Final 8/17/2020 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 8/17/2020 Corrections Issued MICHEL ABAJAN
PLUMBING-Final 8/17/2020 Corrections Issued MICHEL ABAJAN
Smoke Detectors 8/17/2020 Approved MICHEL ABAJAN
ELECTRICAL-Final 1/22/2021 Not Ready for Inspection JENNIFER RABUCHIN
Final 1/22/2021 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 6/3/2022 Corrections Issued JENNIFER RABUCHIN
Final 6/3/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Final 6/3/2022 Corrections Issued JENNIFER RABUCHIN
Pre-Inspection 6/26/2026 Corrections Issued JENNIFER RABUCHIN