10771 W BELLAGIO ROAD 90077

Certificate Information: 10771 W BELLAGIO ROAD 90077

Application / Permit
18016-20000-01444
Plan Check / Job No.
B18VN00781
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR INTERIOR REMODEL TO (E) DWELLING AND ADD 36'0" X 12'0" NEW COVERED PATIO.
Permit Issued
Issued on 4/3/2018
Issuing Office
Valley
Current Status
CofO Issued on 12/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/16/2018 APPLICANT
Assigned to Plan Check Engineer 1/25/2018 STANLEY RAAP
Corrections Issued 1/30/2018 STANLEY RAAP
Quality Review Completed 2/1/2018 CHON CHIO KUO
Building Plans Picked Up 2/2/2018 APPLICANT
Applicant returned to address corrections 3/15/2018 STANLEY RAAP
Plan Check Approved 4/2/2018 STANLEY RAAP
Issued 4/3/2018 LADBS
CofO in Progress 10/28/2021 CHRISTOPHER WILSON
Permit Finaled 12/21/2021 DANIEL ORRANTE
CofO Issued 12/21/2021 DANIEL ORRANTE
Permit Finaled 12/21/2021 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/28/2018 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 2/28/2018 MARKOS PEREZ-BRAN
Sewer availability Cleared 2/28/2018 MARKOS PEREZ-BRAN
ZA Case Cleared 2/28/2018 DENNIS CHEW
ZA Case Cleared 2/28/2018 DENNIS CHEW
ZA Case Cleared 2/28/2018 DENNIS CHEW
ZA Case Cleared 2/28/2018 DENNIS CHEW
ZA Case Cleared 2/28/2018 DENNIS CHEW
ZA Case Cleared 2/28/2018 DENNIS CHEW
Public Works-Highway Ded. Cleared 2/28/2018 MARKOS PEREZ-BRAN
Public Works-Open Permits Cleared 2/28/2018 MARKOS PEREZ-BRAN
Public Works-Sewers Cleared 2/28/2018 MARKOS PEREZ-BRAN
Grading Pre-Inspection Cleared 3/20/2018 BRIAN OLSON
CPC Cleared 4/2/2018 DENNIS CHEW
GPI Written Notices Cleared 4/2/2018 STANLEY RAAP

Contact Information

Architect Gormally, Vincent E; Lic. No.: C27133 10752 CHARNOCK ROAD      LOS ANGELES, CA 900346202
Contractor Mathew Lloyd Homes Llc; Lic. No.: 936706-B 2331 SIRIUS STREET      THOUSAND OAKS, CA 91360
Engineer Golabtounkar, Tony Hamid; Lic. No.: C49104 18345 VENTURA BLVD #208      TARZANA, CA 91356

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/12/2018 Partial Approval ANTHONY ANDERSON
Deputy Drilled-In Anchors 4/18/2018 Conditional Approval JOEL LAUNCHBAUGH
Deputy Drilled-In Anchors 4/23/2018 Conditional Approval ANTHONY ANDERSON
Footing/Foundation/Slab 4/24/2018 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 5/1/2018 Conditional Approval ANTHONY ANDERSON
Footing/Foundation/Slab 5/4/2018 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 5/7/2018 Conditional Approval ANTHONY ANDERSON
Deputy Wood Construction 5/17/2018 Conditional Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 5/18/2018 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 6/6/2018 Partial Approval MATT KELLERMAN
Deputy Wood Construction 8/23/2018 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 9/7/2018 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 9/12/2018 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 9/12/2018 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 9/24/2018 Partial Approval JOHN LUMB
Deputy Reinf. Concrete 9/28/2018 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/1/2018 Conditional Approval MATT KELLERMAN
Deputy Reinf. Concrete 10/19/2018 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/22/2018 Conditional Approval CHRISTOPHER WILSON
Wood Frame 10/23/2018 Partial Inspection CHRISTOPHER WILSON
Wood Frame 10/31/2018 Partial Approval MATT KELLERMAN
Insulation 11/5/2018 Approved MATT KELLERMAN
Drywall Nailing 11/14/2018 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 1/2/2019 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 3/19/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 3/21/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 3/26/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 4/2/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 4/5/2019 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 4/30/2019 Partial Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 5/1/2019 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 6/11/2019 Approved CHRISTOPHER WILSON
Wood Frame 6/11/2019 Approved CHRISTOPHER WILSON
Drywall Nailing 6/13/2019 Approved CHRISTOPHER WILSON
Pre-Inspection 6/28/2019 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 1/18/2020 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 1/25/2020 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 4/1/2020 Partial Approval CHRISTOPHER WILSON
Masonry Wall/Backfill 4/15/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 5/8/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/19/2020 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 5/19/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 6/2/2020 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 6/3/2020 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 6/15/2020 Approved CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 6/30/2020 Corrections Issued CHRISTOPHER WILSON
Masonry Wall/Backfill 6/30/2020 Partial Approval CHRISTOPHER WILSON
Deputy Wood Construction 7/1/2020 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 7/2/2020 Partial Approval CHRISTOPHER WILSON
Deputy Wood Construction 8/18/2020 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 8/27/2020 Corrections Issued CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 10/8/2020 Not Ready for Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 10/8/2020 Not Ready for Inspection CHRISTOPHER WILSON
Wall Anchors 10/16/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 11/5/2020 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 11/5/2020 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 11/6/2020 Partial Approval CHRISTOPHER WILSON
Wall Anchors 11/16/2020 Not Ready for Inspection CHRISTOPHER WILSON
Insulation 11/19/2020 Partial Approval CHRISTOPHER WILSON
Wood Frame 11/19/2020 Partial Approval CHRISTOPHER WILSON
Deputy Wood Construction 11/25/2020 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 12/3/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Insulation 12/7/2020 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 12/7/2020 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 12/8/2020 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 12/10/2020 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 12/11/2020 Partial Approval ANTHONY MCDOWALL
Insulation 12/11/2020 Partial Approval ANTHONY MCDOWALL
Insulation 12/17/2020 Not Ready for Inspection MATT KELLERMAN
Pre-Inspection 12/17/2020 Not Ready for Inspection MATT KELLERMAN
Insulation 12/23/2020 Not Ready for Inspection MATT KELLERMAN
Interior/Exterior Lathing 12/23/2020 Not Ready for Inspection MATT KELLERMAN
Smoke Detectors 12/23/2020 Not Ready for Inspection MATT KELLERMAN
Wood Frame 12/23/2020 Partial Approval MATT KELLERMAN
Insulation 12/30/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Green Building Rough 1/4/2021 Partial Approval CHRISTOPHER WILSON
Insulation 1/4/2021 Partial Approval CHRISTOPHER WILSON
Wood Frame 1/4/2021 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 1/5/2021 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 1/11/2021 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 1/15/2021 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 2/5/2021 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 2/10/2021 Partial Approval CHRISTOPHER WILSON
Smoke Detectors 2/18/2021 Corrections Issued CHRISTOPHER WILSON
Interior/Exterior Lathing 2/22/2021 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Wood Construction 2/26/2021 Conditional Approval CHRISTOPHER WILSON
Pre-Inspection 3/3/2021 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 3/18/2021 Partial Approval CARLOS MATAMOROS
Pre-Inspection 4/22/2021 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 4/22/2021 Partial Approval CHRISTOPHER WILSON
Smoke Detectors 5/7/2021 Not Ready for Inspection CHRISTOPHER WILSON
Special/Order Compliance 6/11/2021 Not Ready for Inspection ANTHONY MCDOWALL
Final 8/5/2021 Not Ready for Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 8/5/2021 SGSOV Not Ready CHRISTOPHER WILSON
Smoke Detectors 8/5/2021 Not Ready for Inspection CHRISTOPHER WILSON
Wood Frame 8/5/2021 Approved CHRISTOPHER WILSON
Final 9/16/2021 Not Ready for Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 9/16/2021 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 9/16/2021 Approved CHRISTOPHER WILSON
Final 10/18/2021 Corrections Issued CHRISTOPHER WILSON
Final 10/22/2021 Not Ready for Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 10/25/2021 SGSOV Approved CHRISTOPHER WILSON
Special/Order Compliance 10/25/2021 Not Ready for Inspection CHRISTOPHER WILSON
Final 10/27/2021 Not Ready for Inspection CHRISTOPHER WILSON
Final 10/28/2021 Conditional Approval CHRISTOPHER WILSON