10345 W OLYMPIC BLVD 90064
Certificate Information: 10345 W OLYMPIC BLVD 90064
- Application / Permit
- 18016-10004-38517
- Plan Check / Job No.
- B20LA03879
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Supplemental to 18016-10000-38517: Add 12' (H) x 20' (L) wall to building
- Permit Issued
- Issued on 2/27/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 10/23/2020
Permit Application Status History
| Submitted | 2/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/26/2020 | HERNAN ARREOLA |
| Plan Check Approved | 2/26/2020 | HERNAN ARREOLA |
| Issued | 2/27/2020 | LADBS |
| Permit Finaled | 10/22/2020 | PAUL DAVIDSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Clune Construction Company L P; Lic. No.: 732107-B | 350 SOUTH GRAND AVE #1600 LOS ANGELES, CA 90071 |
| Engineer | Hershberg,, Mark Aaron; Lic. No.: S5078 | 6080 CENTER DR STE 300 LOS ANGELES, CA 90045 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 2/28/2020 | Not Ready for Inspection | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 2/28/2020 | Approved | JEFF BYTHEWAY |
| Light Gage Steel Frame | 2/28/2020 | Approved | JEFF BYTHEWAY |
| Drywall Nailing | 3/3/2020 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 3/4/2020 | Approved | PAUL DAVIDSON |
| Interior/Exterior Lathing | 3/4/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Interior/Exterior Lathing | 3/6/2020 | Approved | PAUL DAVIDSON |
| Special/Order Compliance | 9/2/2020 | Partial Inspection | PAUL DAVIDSON |
| Final | 10/22/2020 | Permit Finaled | PAUL DAVIDSON |
| Green Building Final | 10/22/2020 | Approved | PAUL DAVIDSON |
| Smoke Detectors | 10/22/2020 | Approved | PAUL DAVIDSON |