200 WORLD WAY 90045

Certificate Information: 200 WORLD WAY 90045

Application / Permit
18016-10003-19522
Plan Check / Job No.
B21LA22480
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(3) Airport Building
Work Description
Supplemental permit to 18016-10000-19522 (PH-1F) for revisions to Architectural, Fire Life Safety, and Structural Plans (DCN-129).
Permit Issued
Issued on 4/22/2022
Issuing Office
Metro
Current Status
Permit Finaled on 11/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/1/2021 APPLICANT
Assigned to Plan Check Engineer 12/9/2021 RODOLFO ARIAS
Corrections Issued 12/13/2021 RODOLFO ARIAS
Quality Review Completed 12/13/2021 LIPING TENG
Applicant returned to address corrections 12/16/2021 RODOLFO ARIAS
Applicant returned to address corrections 12/22/2021 RODOLFO ARIAS
Applicant returned to address corrections 1/5/2022 RODOLFO ARIAS
Applicant returned to address corrections 1/12/2022 RODOLFO ARIAS
Applicant returned to address corrections 1/19/2022 RODOLFO ARIAS
Applicant returned to address corrections 1/26/2022 RODOLFO ARIAS
Applicant returned to address corrections 2/2/2022 RODOLFO ARIAS
Applicant returned to address corrections 2/9/2022 RODOLFO ARIAS
Applicant returned to address corrections 3/2/2022 RODOLFO ARIAS
Applicant returned to address corrections 4/7/2022 RODOLFO ARIAS
Applicant returned to address corrections 4/13/2022 RODOLFO ARIAS
Plan Check Approved 4/14/2022 RODOLFO ARIAS
No Progress 4/15/2022 RODOLFO ARIAS
Plan Check Approved 4/15/2022 RODOLFO ARIAS
Issued 4/22/2022 APPLICANT
Permit Finaled 11/14/2024 ALAN NOVAK
Permit Finaled 11/14/2024 ALAN NOVAK

Permit Application Clearance Information

Project Permit Cleared 12/21/2021 VINITA WASKOW
Specific Plan Cleared 12/23/2021 PEDRO AYALA
Sewer availability Cleared 12/28/2021 DINAH GARIN
City owned building/parcel Cleared 12/29/2021 RODOLFO ARIAS
Low Impact Development Cleared 12/29/2021 AMMAR ELTAWIL
Stormwater Pollution Mitigatn Cleared 12/29/2021 AMMAR ELTAWIL
Eng Process Fee Ord 176,300 Cleared 12/30/2021 DINAH GARIN
DAS Clearance Cleared 4/5/2022 SHINE LIN
Airport buildings Cleared 4/15/2022 ANDREW KO
Fire Marshall Fire Life Safety Cleared 4/15/2022 ANDREW KO

Contact Information

Architect Circenis,, John Robert; Lic. No.: C24596 1133 24TH #13      SANTA MONICA, CA 90403
Contractor Hensel Phelps Construction Co; Lic. No.: 1020262-B 420 SIXTH AVENUE      GREELEY, CO 80631
Engineer Mino,, Trevor Joseph; Lic. No.: C79257 3754 BRILLIANT DR      LOS ANGELES, CA 90065
Engineer Moyle,, Ted Roger; Lic. No.: FP1867 1102 12TH ST UNIT 4      SANTA MONICA, CA 90403
Engineer Rees,, Simon; Lic. No.: S4897 1246 11TH ST      MANHATTAN BEACH, CA 90266

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Final 11/14/2024 Permit Finaled ALAN NOVAK
Reinforced Concrete Frame 11/14/2024 Approved ALAN NOVAK