8500 N BALBOA BLVD # 170 91325
Certificate Information: 8500 N BALBOA BLVD # 170 91325
- Application / Permit
- 18016-10002-32111
- Plan Check / Job No.
- B19LA11353
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (12) Manufacturing
- Work Description
- INTERIOR ALTERATION OF EXISTING STORAGE AND OFFICE SPACE IN A MANUFACTURING BUILDING. 5487 SF PORTION OF EXISTING MANUFACTUING BUILDING TO CONVERT A PORTION OF ACCESSORY OFFICE SPACE TO STORAGE AND ALTER REMAINING PORTION OF OFFICE AREA AND EXISTING STORAGE AREA..
- Permit Issued
- Issued on 4/22/2020
- Issuing Office
- Current Status
- CofO Issued on 1/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2019 | APPLICANT |
| Green Plans Picked Up | 6/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2019 | STANLEY RAAP |
| Corrections Issued | 6/24/2019 | STANLEY RAAP |
| Quality Review Completed | 7/3/2019 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 7/12/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 10/8/2019 | APPLICANT |
| Applicant returned to address corrections | 3/4/2020 | STANLEY RAAP |
| Plan Check Approved | 3/6/2020 | STANLEY RAAP |
| Issued | 4/22/2020 | APPLICANT |
| CofO in Progress | 3/23/2021 | JEFFREY FULTON |
| CofO Issued | 1/11/2022 | JEFFREY DURAN |
| Permit Finaled | 1/11/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| Green Code | Cleared | 2/28/2020 | COLIN LOREDO |
| DAS Clearance | Cleared | 3/4/2020 | SHINE LIN |
| ZA Case | Cleared | 3/4/2020 | MIGUEL GAMBOA |
| ZA Case | Cleared | 3/4/2020 | MIGUEL GAMBOA |
Contact Information
| Architect | Mickow,, John M; Lic. No.: C28429 | 137 GORDON ROAD WALNUT CREEK, CA 94598 |
| Contractor | B N Builders Inc; Lic. No.: 799131-B | 2601 4TH AVE #350 SEATTLE, WA 98121 |
| Engineer | Tso,, Leslie; Lic. No.: S3073 | 511 MISSION ST SOUTH PASADENA, CA 910303035 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 5/21/2020 | Approved | HAMID PISHEHVAR |
| Light Gage Steel Frame | 5/27/2020 | Partial Inspection | JEFFREY FULTON |
| Insulation | 5/29/2020 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 6/4/2020 | Approved | JEFFREY FULTON |
| Green Building Rough | 6/4/2020 | Approved | JEFFREY FULTON |
| Wood Frame | 6/4/2020 | Partial Inspection | JEFFREY FULTON |
| Deputy Drilled-In Anchors | 6/19/2020 | Conditional Approval | JEFFREY FULTON |
| Deputy Reinf. Concrete | 6/19/2020 | Conditional Approval | JEFFREY FULTON |
| Light Gage Steel Frame | 7/21/2020 | Partial Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 7/21/2020 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 8/10/2020 | No Access for Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 8/10/2020 | No Access for Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 8/14/2020 | Approved | JEFFREY FULTON |
| Final | 8/26/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Final | 8/26/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 8/26/2020 | Approved | JEFFREY FULTON |
| Smoke Detectors | 8/26/2020 | Approved | JEFFREY FULTON |
| Final | 9/11/2020 | Partial Inspection | JEFFREY FULTON |
| Green Building Final | 9/11/2020 | Approved | JEFFREY FULTON |
| Wood Frame | 9/11/2020 | Approved | JEFFREY FULTON |
| Final | 10/7/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 12/18/2020 | OK to Issue CofO | JEFFREY FULTON |