777 N VINE ST 90038

Certificate Information: 777 N VINE ST 90038

Application / Permit
18016-10002-20460
Plan Check / Job No.
B22LA24120
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
SOFT STORY RETROFIT PER LAMC DIVISION 93. INSTALL (N) SEVEN STEEL SPECIAL CANTILEVER COLUMN SYSTEMS. SUPPLEMENTAL PERMIT FOR DETAIL CHANGE.
Permit Issued
Issued on 11/30/2022
Issuing Office
Metro
Current Status
Permit Finaled on 4/15/2024

Permit Application Status History

Plan Check Approved 11/30/2022 VARAND SARKISIAN
Issued 11/30/2022 APPLICANT
Permit Finaled 4/15/2024 JACOB MYERS

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Design Concepts; Lic. No.: 558701-B 3340 RIVERSIDE DR #M      CHINO, CA 91710
Engineer Bhakta,, Shashikant Rambhai; Lic. No.: C40527 13830 MONTEVERDE DRIVE      CHINO HILLS, CA 91710

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Other (see comments) 12/20/2022 Conditional Approval VAHE KELEDJIAN
Deputy Steel/Welding 12/20/2022 Conditional Approval VAHE KELEDJIAN
Excavation/Setback/Form/Re-Bar 12/20/2022 Corrections Issued VAHE KELEDJIAN
Deputy Drilled-In Anchors 12/21/2022 Conditional Approval VAHE KELEDJIAN
Deputy Reinf. Concrete 1/3/2023 Conditional Approval BRUCE CAMPBELL
Deputy Reinf. Concrete 1/4/2023 Conditional Approval BRUCE CAMPBELL
Structural Steel Frame 1/5/2023 Partial Approval BRUCE CAMPBELL
Excavation/Setback/Form/Re-Bar 1/18/2023 Conditional Approval VAHE KELEDJIAN
Wood Frame 1/18/2023 Conditional Approval VAHE KELEDJIAN
Deputy Reinf. Concrete 1/23/2023 Conditional Approval VAHE KELEDJIAN
Interior/Exterior Lathing 1/26/2023 Not Ready for Inspection BRUCE CAMPBELL
Excavation/Setback/Form/Re-Bar 3/24/2023 Corrections Issued VAHE KELEDJIAN
Wood Frame 3/24/2023 Not Ready for Inspection VAHE KELEDJIAN
Deputy Drilled-In Anchors 4/11/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 4/11/2023 Conditional Approval MICHAEL ROSENBERG
Structural Steel Frame 4/19/2023 Corrections Issued VAHE KELEDJIAN
Excavation/Setback/Form/Re-Bar 6/23/2023 Conditional Approval DARRYL ARNOLD
Wood Frame 8/11/2023 No Access for Inspection DARRYL ARNOLD
Wood Frame 8/15/2023 Conditional Approval VAHE KELEDJIAN
Interior/Exterior Lathing 8/25/2023 Partial Approval VAHE KELEDJIAN
Deputy Reinf. Concrete 11/21/2023 Approved JACOB MYERS
Deputy Drilled-In Anchors 12/18/2023 Partial Approval JACOB MYERS
Deputy Reinf. Concrete 12/20/2023 Partial Approval JACOB MYERS
Excavation/Setback/Form/Re-Bar 1/4/2024 Approved JACOB MYERS
Structural Steel Frame 1/4/2024 Approved JACOB MYERS
Deputy Reinf. Concrete 1/8/2024 Partial Approval JACOB MYERS
Wood Frame 1/19/2024 Partial Approval JACOB MYERS
Deputy Wood Construction 1/22/2024 Conditional Approval JACOB MYERS
Wood Frame 1/23/2024 Approved JACOB MYERS
Interior/Exterior Lathing 1/29/2024 Approved JACOB MYERS
Final 4/12/2024 Partial Approval JACOB MYERS
Final 4/15/2024 Permit Finaled JACOB MYERS