1453 W TEMPLE ST 90026

Certificate Information: 1453 W TEMPLE ST 90026

Application / Permit
18016-10002-11155
Plan Check / Job No.
B20LA08380
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
SUPPLEMENTAL PERMIT TO 18016-10000-11155 TO REVISE FLOOR PLANS ON BOTH FLOORS. INCLUDES PARKING RESTRIPE OF PARKING LOT.
Permit Issued
Issued on 8/21/2020
Issuing Office
Current Status
Permit Finaled on 3/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 LAWRENCE QUIRANTE
Corrections Issued 5/22/2020 LAWRENCE QUIRANTE
Quality Review Completed 5/29/2020 ALLEN MANALANSAN
Building Plans Picked Up 6/1/2020 APPLICANT
Applicant returned to address corrections 6/11/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 7/27/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 8/14/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 8/20/2020 LAWRENCE QUIRANTE
Plan Check Approved 8/21/2020 LAWRENCE QUIRANTE
Issued 8/21/2020 APPLICANT
Permit Finaled 3/1/2021 KATY RAMIREZ

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/12/2020 RENZ SORIANO
Sewer availability Cleared 6/12/2020 RENZ SORIANO
Specific Plan Cleared 7/15/2020 LAWRENCE QUIRANTE
DAS Clearance Cleared 8/5/2020 LAWRENCE QUIRANTE

Contact Information

Contractor Owner-Builder       ,
Engineer Greco, Adam Matthew; Lic. No.: S4077 1470 WESTERLY TERRACE      LOS ANGELES, CA 90026

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Structural Steel Frame 8/27/2020 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 9/3/2020 Partial Approval KATY RAMIREZ
Insulation 9/9/2020 Partial Approval KATY RAMIREZ
Drywall Nailing 9/16/2020 Not Ready for Inspection KATY RAMIREZ
Drywall Nailing 9/18/2020 Partial Approval KATY RAMIREZ
Drywall Nailing 9/23/2020 Approved RUSSELL BONVOULOIR
Drywall Nailing 9/29/2020 Not Ready for Inspection KATY RAMIREZ
Special/Order Compliance 10/1/2020 Partial Inspection KATY RAMIREZ
Pre-Inspection 10/22/2020 Approved KATY RAMIREZ
Drywall Nailing 12/21/2020 No Access for Inspection KATY RAMIREZ
Insulation 1/20/2021 Not Ready for Inspection KATY RAMIREZ
METHANE-Final 2/19/2021 Approved KATY RAMIREZ
Final 2/22/2021 Not Ready for Inspection KATY RAMIREZ
Final 2/24/2021 Not Ready for Inspection KATY RAMIREZ