3373 N COLDWATER CANYON AVE 91604
Certificate Information: 3373 N COLDWATER CANYON AVE 91604
- Application / Permit
- 18016-10001-36737
- Plan Check / Job No.
- B19LA16111
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO PERMIT 18016-10000-36737 SECOND FLOOR ADDITION TO (E) S.F.D, TO CREATE 2 BEDROOMS AND BATH OVER (E) SECOND FLOOR PATIO AND GARAGE FLAT ROOF. (ADDITION: 792SF), NEW SECOND FLOOR BALCONY (140 SF). REMOVE (E) SECOND FLOOR CANVAS COVERED PATIO, REMOVE (E) GARAGE FLAT ROOF.
- Permit Issued
- Issued on 2/21/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2019 | RACHEL BEYENE |
| Green Plans Picked Up | 8/15/2019 | APPLICANT |
| Corrections Issued | 8/27/2019 | RACHEL BEYENE |
| Quality Review Completed | 9/12/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 9/13/2019 | APPLICANT |
| Applicant returned to address corrections | 12/11/2019 | RACHEL BEYENE |
| Applicant returned to address corrections | 12/30/2019 | RACHEL BEYENE |
| Applicant returned to address corrections | 2/18/2020 | RACHEL BEYENE |
| Plan Check Approved | 2/21/2020 | RAHEL BEYENE |
| Issued | 2/21/2020 | LADBS |
| CofO in Progress | 1/25/2021 | ARAM AVEDISIAN |
| Permit Finaled | 8/4/2022 | DANIEL ORRANTE |
| CofO Issued | 8/4/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/4/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2019 | THOMAS LANG |
| Low Impact Development | Cleared | 12/6/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 12/6/2019 | THOMAS LANG |
| Sewer availability | Cleared | 12/6/2019 | THOMAS LANG |
| Green Code | Cleared | 12/17/2019 | DONALD CRICHLOW |
| Miscellaneous | Cleared | 12/31/2019 | MARC WOERSCHING |
| Private street | Cleared | 12/31/2019 | MARC WOERSCHING |
| Specific Plan | Cleared | 2/7/2020 | TRACY WILLIAMS |
| BHO/Hillside ordinance | Cleared | 2/18/2020 | APEKSHYA BAJRACHARYA |
| BHO/Hillside ordinance | Cleared | 2/18/2020 | APEKSHYA BAJRACHARYA |
| BHO/Hillside ordinance | Cleared | 2/18/2020 | APEKSHYA BAJRACHARYA |
Contact Information
| Contractor | Haydu Construction Inc; Lic. No.: 841653-B | 1933 257TH ST LOMITA, CA 90717 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/11/2020 | Corrections Issued | JEFFREY PARD |
| ELECTRICAL-Rough | 3/11/2020 | Approved | JEFFREY PARD |
| Green Building Rough | 3/11/2020 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 3/11/2020 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 3/11/2020 | Corrections Issued | JEFFREY PARD |
| Verify Sprinkler Sign Off | 3/11/2020 | Approved | JEFFREY PARD |
| Insulation | 3/24/2020 | Approved | CHARLES POWELL |
| Interior/Exterior Lathing | 3/24/2020 | Not Ready for Inspection | CHARLES POWELL |
| BUILDING-Rough-Frame | 3/26/2020 | Partial Approval | BEAU COLLINS |
| Insulation | 3/26/2020 | Approved | BEAU COLLINS |
| Drywall Nailing | 4/2/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Rough | 4/2/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 4/2/2020 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/2/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/6/2020 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/18/2020 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 12/18/2020 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 12/18/2020 | Approved | ARAM AVEDISIAN |
| Final | 12/18/2020 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 12/18/2020 | Approved | ARAM AVEDISIAN |
| Green Building Final | 12/18/2020 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 12/18/2020 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 12/18/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Final | 12/18/2020 | Approved | ARAM AVEDISIAN |
| Smoke Detectors | 12/18/2020 | Approved | ARAM AVEDISIAN |
| Final | 1/25/2021 | OK to Issue CofO | ARAM AVEDISIAN |