318 S MARIPOSA AVE 90020

Certificate Information: 318 S MARIPOSA AVE 90020

Application / Permit
18016-10001-35623
Plan Check / Job No.
B22LA13986
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT-STORY RETROFIT AS PER LABC CH.93. SUPPLEMENTAL TO PERMIT #18016-10000-35623. CHANGE OF EOR.
Permit Issued
Issued on 8/9/2022
Issuing Office
Metro
Current Status
Permit Finaled on 2/28/2023

Permit Application Status History

Submitted 7/18/2022 APPLICANT
Assigned to Plan Check Engineer 7/21/2022 JESSE VIDUYA
Corrections Issued 7/26/2022 JESSE VIDUYA
Quality Review Completed 7/27/2022 HANS SANTIAGO
Building Plans Picked Up 7/29/2022 APPLICANT
Plan Check Approved 8/9/2022 JESSE VIDUYA
Issued 8/9/2022 APPLICANT
Permit Finaled 2/27/2023 VAHE KELEDJIAN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor S F T Construction Corp; Lic. No.: 1009086-B 322 6TH STREET UNIT 4      SAN FRANCISCO, CA 94103
Engineer Tajvidi,, Seyed Mohammad; Lic. No.: C84559 9163 LEROY STREET      SAN GABRIEL, CA 91775

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/12/2022 Approved BRUCE CAMPBELL
Deputy Wood Construction 9/23/2022 Conditional Approval DARRYL ARNOLD
Wood Frame 9/23/2022 Corrections Issued BRUCE CAMPBELL
Deputy Drilled-In Anchors 10/20/2022 Conditional Approval DARRYL ARNOLD
Deputy Wood Construction 10/20/2022 Conditional Approval DARRYL ARNOLD
Deputy Steel/Welding 10/21/2022 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Concrete 10/24/2022 Conditional Approval DARRYL ARNOLD
Final 2/27/2023 Permit Finaled VAHE KELEDJIAN
METHANE-Final 2/27/2023 Approved VAHE KELEDJIAN