2000 W MIRAMAR ST 90057
Certificate Information: 2000 W MIRAMAR ST 90057
- Application / Permit
- 18016-10001-21509
- Plan Check / Job No.
- B20LA17045
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SUPPLEMENTAL TO 18016-10000-21509 TO EXPAND LOBBY UNDER (E) ROOFLINE WITH EXTENDED SLAB ON GRADE + NEW STOREFRONT ENTRY
- Permit Issued
- Issued on 10/22/2020
- Issuing Office
- Current Status
- Permit Finaled on 5/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2020 | ERIC WONG |
| Corrections Issued | 10/1/2020 | ERIC WONG |
| Plan Check Approved | 10/14/2020 | ERIC WONG |
| Issued | 10/22/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 10/23/2020 | APPLICANT |
| Building Plans Picked Up | 12/17/2020 | APPLICANT |
| Permit Finaled | 5/3/2021 | DANIEL COLLINS |
Permit Application Clearance Information
| Public Housing | Cleared | 10/13/2020 | LUIS ALVAREZ |
| DAS Clearance | Cleared | 10/14/2020 | ERIC WONG |
Contact Information
| Architect | Brooks,, Angela C; Lic. No.: C27554 | 616 BOCCACCIO AVENUE VENICE, CA 90291 |
| Contractor | Path Construction Southwest Llc; Lic. No.: 1040576-B | 125 E ALGONQUIN RD ARLINGTON HEIGHTS, IL 60005 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 5/3/2021 | Permit Finaled | DANIEL COLLINS |
| METHANE-Final | 5/3/2021 | Approved | DANIEL COLLINS |
| METHANE-Rough | 5/3/2021 | Approved | DANIEL COLLINS |
| Reinforced Concrete Frame | 5/3/2021 | Approved | DANIEL COLLINS |
| Smoke Detectors | 5/3/2021 | Approved | DANIEL COLLINS |