12530 W CLOUD LANE 90049
Certificate Information: 12530 W CLOUD LANE 90049
- Application / Permit
- 18016-10001-13056
- Plan Check / Job No.
- B19LA00339
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Supplemental permit to 18016-10000-13056 to add 4'-11"x 19'-4" new covered balcony, extend 3'-6"x 63'-0" roof eave, add new grade beam and caissons foundations per soil report and engineer design
- Permit Issued
- Issued on 3/18/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO in Progress on 5/27/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2019 | VU NGUYEN |
| Corrections Issued | 1/29/2019 | VU NGUYEN |
| Quality Review Completed | 1/30/2019 | MICHAEL PEREZ |
| Building Plans Picked Up | 2/12/2019 | APPLICANT |
| Plan Check Approved | 2/28/2019 | VU NGUYEN |
| Issued | 3/18/2019 | LADBS |
| CofO in Progress | 5/27/2026 | KEVIN SARGSYAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Schmidt, James Warren Jr; Lic. No.: C22142 | 4380 IRVINE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Shramek Building Company; Lic. No.: 492534-B | 6032 JASONWOOD DRIVE HUNTINGTON BEACH, CA 92648 |
| Engineer | Mallak, Nabil Michel; Lic. No.: S5351 | 6385 GREEN VALLEY CIR 218 CULVER CITY, CA 90230 |
| Geologist | Daugherty, Daniel Thomas; Lic. No.: EG2569 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/22/2019 | Corrections Issued | KENNETH NAGLE |
| Footing/Foundation/Slab | 3/29/2019 | Partial Approval | KENNETH NAGLE |
| Deputy Steel/Welding | 6/25/2019 | Conditional Approval | TIM CHRISTENSEN |
| ELECTRICAL-Rough | 3/31/2021 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2021 | Partial Approval | JUAN VALENZUELA |
| HVAC-Rough | 4/23/2021 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 5/26/2026 | Approved | KEVIN SARGSYAN |
| Final | 5/26/2026 | OK to Issue CofO | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 5/26/2026 | Approved | KEVIN SARGSYAN |
| Green Building Final | 5/26/2026 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 5/26/2026 | Approved | KEVIN SARGSYAN |
| Smoke Detectors | 5/26/2026 | Approved | KEVIN SARGSYAN |
| Special/Order Compliance | 5/27/2026 | Corrections Issued | ANDREW NAVE |