124 E MAST MALL 90292
Certificate Information: 124 E MAST MALL 90292
- Application / Permit
- 18016-10001-09501
- Plan Check / Job No.
- B20LA02420
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REBUILDING ROOF STAIR SHAFT ENCLOSURE WITH MAX 5FT. ROOF CANTILEVER OVERHANG. SEPARAT PERMIT FOR ROOF DECK ART PIECE.
- Permit Issued
- Issued on 9/23/2020
- Issuing Office
- Current Status
- Permit Finaled on 4/1/2021
Permit Application Status History
| Submitted | 2/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2020 | JOE VO |
| Corrections Issued | 2/25/2020 | JOE VO |
| Quality Review Completed | 3/2/2020 | KEN GILL |
| Building Plans Picked Up | 3/9/2020 | APPLICANT |
| Applicant returned to address corrections | 4/13/2020 | JOE VO |
| Green Plans Picked Up | 4/22/2020 | APPLICANT |
| Applicant returned to address corrections | 7/13/2020 | JOE VO |
| Plan Check Approved | 9/21/2020 | JOE VO |
| Issued | 9/23/2020 | APPLICANT |
| Permit Finaled | 4/1/2021 | JOHNNY MIRANDA |
Permit Application Clearance Information
| Green Code | Cleared | 4/22/2020 | COLIN LOREDO |
| ZA Case | Cleared | 9/4/2020 | RICHARD REASER |
| ZA Case | Cleared | 9/4/2020 | RICHARD REASER |
| ZI | Cleared | 9/4/2020 | RICHARD REASER |
| Coastal Zone | Cleared | 9/15/2020 | MAXFIELD VERMY |
| Specific Plan | Cleared | 9/15/2020 | MAXFIELD VERMY |
| Specific Plan | Cleared | 9/21/2020 | PEDRO AYALA |
Contact Information
| Contractor | Home Front Build Inc; Lic. No.: 962293-B | 3926 GLENALBYN DRIVE LOS ANGELES, CA 90065 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Structural Steel Frame | 11/19/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2021 | Approved | JUAN VALENZUELA |
| Structural Steel Frame | 1/21/2021 | Approved | JUAN VALENZUELA |
| Insulation | 1/25/2021 | Approved | DAVID HEINE |
| Drywall Nailing | 2/17/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 2/17/2021 | Partial Approval | JOHNNY MIRANDA |
| Final | 4/1/2021 | Permit Finaled | JOHNNY MIRANDA |
| Green Building Final | 4/1/2021 | Approved | JOHNNY MIRANDA |
| METHANE-Final | 4/1/2021 | Approved | JOHNNY MIRANDA |
| Smoke Detectors | 4/1/2021 | Approved | JOHNNY MIRANDA |