2717 W SOUTHWEST DR 90043
Certificate Information: 2717 W SOUTHWEST DR 90043
- Application / Permit
- 18016-10001-07825
- Plan Check / Job No.
- B20LA17807
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (27) Artist-in-Residence
- Work Description
- CHANGE OF USE FROM (E) FACTORY TO LIVE WORK ARTIST & RESIDENCE (Joint living and work quarter), BUILDING TO BE FULLY SPRINKLERED.
- Permit Issued
- Issued on 12/7/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2020 | SAMUEL GONZALEZ |
| Corrections Issued | 10/6/2020 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 3/9/2021 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 8/9/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 9/20/2021 | TSE MING HUANG |
| Plan Check Approved | 1/18/2022 | STANLEY RAAP |
| Building Plans Picked Up | 1/20/2022 | APPLICANT |
| Issued | 12/7/2022 | APPLICANT |
| CofO in Progress | 3/4/2024 | JOSE MACIAS |
| CofO in Progress | 4/19/2024 | DAVID FEILER |
| Permit Finaled | 4/29/2024 | DEROLD HAUFF |
| CofO Issued | 4/29/2024 | DEROLD HAUFF |
| Permit Finaled | 4/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| ZA Case | Cleared | 4/5/2021 | DANIEL CORONADO |
| ZA Case | Cleared | 4/5/2021 | DANIEL CORONADO |
| Miscellaneous | Cleared | 4/29/2021 | DANIEL CORONADO |
| Address approval | Cleared | 5/7/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 5/11/2021 | CECILIO NAVARRO |
| "D" conditions | Cleared | 5/27/2021 | KYLE WINSTON |
| Community Plan Implem. Overlay | Cleared | 5/27/2021 | KYLE WINSTON |
| CPC | Cleared | 10/1/2021 | DANIEL CORONADO |
Contact Information
| Architect | Puskar, Heidi M; Lic. No.: C28223 | 368 S MIRALESTE DR 377 SAN PEDRO, CA 90732 |
| Contractor | Mac Gregor Keith; Lic. No.: 777652-B | 505 VIA PROVIDENCIA BURBANK, CA 91501 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/9/2023 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 1/18/2023 | Approved | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 1/31/2023 | Approved | ENRIQUE MIRELES |
| Deputy Steel/Welding | 1/31/2023 | Approved | ENRIQUE MIRELES |
| Structural Steel Frame | 2/1/2023 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 2/1/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/2/2023 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 6/2/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/2/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/26/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 6/26/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 7/12/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 8/3/2023 | Approved | ENRIQUE MIRELES |
| Shower Pan | 8/3/2023 | Approved | ENRIQUE MIRELES |
| Final | 2/26/2024 | Corrections Issued | JOSE MACIAS |
| HVAC-Final | 2/26/2024 | Approved | JOSE MACIAS |
| PLUMBING-Final | 2/26/2024 | Approved | JOSE MACIAS |
| Reinforced Masonry Frame | 2/26/2024 | Approved | JOSE MACIAS |
| Smoke Detectors | 2/26/2024 | Approved | JOSE MACIAS |
| Final | 3/1/2024 | OK to Issue CofO | JOSE MACIAS |
| Special/Order Compliance | 3/5/2024 | Approved | ERNESTO CORRAL |
| Special/Order Compliance | 3/5/2024 | Conditional Approval | ENRIQUE MIRELES |