814 N MELROSE HILL 90029

Certificate Information: 814 N MELROSE HILL 90029

Application / Permit
18016-10000-41294
Plan Check / Job No.
B18LA27904
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW BATHROOM ADDITION TO MAIN HOUSE AT REAR ( 8'-4" x 5'-11", 40 SF). ALL WORK PER WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 09/18/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 2/12/2020
Issuing Office
Metro
Current Status
CofO in Progress on 11/4/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/31/2018 APPLICANT
Assigned to Plan Check Engineer 12/31/2018 FARSHAD ALIMOHAMADI
Corrections Issued 12/31/2018 FARSHAD ALIMOHAMADI
Plan Check Approved 8/6/2019 KEVIN MORALES
Issued 2/12/2020 LADBS
CofO in Progress 11/4/2022 COREY HUPP
CofO in Progress 11/4/2022 COREY HUPP

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/31/2018 JEANETTE VONG
Roof/Waste drainage to street Cleared 12/31/2018 JEANETTE VONG
HPOZ Cleared 6/24/2019 LAMBERT GIESSINGER
Hist. Property Cntrct Mgr Appr Cleared 6/24/2019 LAMBERT GIESSINGER

Contact Information

Contractor Carter Design & Remodeling Inc; Lic. No.: 932102-B 23890 COPPERHILL DRIVE #375      VALENCIA, CA 91354

Inspector Information

RUBEN PEREZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT NILES, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
MARK BEVELAQUA, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL SANCHEZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
COREY HUPP, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
EMIL OPFFER, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/8/2021 Partial Approval TIMOTHY MCCURDY
Deputy Drilled-In Anchors 5/4/2021 Partial Approval TIMOTHY MCCURDY
Footing/Foundation/Slab 5/10/2021 Approved TIMOTHY MCCURDY
Insulation 5/26/2021 Approved TIMOTHY MCCURDY
PLUMBING-Rough 5/26/2021 Approved TIMOTHY MCCURDY
Floor/Roof Diaphrgm/Shear Wall 5/27/2021 Partial Approval TIMOTHY MCCURDY
Floor/Roof Diaphrgm/Shear Wall 6/7/2021 Approved TIMOTHY MCCURDY
Interior/Exterior Lathing 6/24/2021 Partial Approval TIMOTHY MCCURDY
BUILDING-Rough-Frame 8/26/2021 Not Ready for Inspection ALFREDO BALANDRA
MERV13>=Rough 8/26/2021 Not Ready for Inspection ALFREDO BALANDRA
Rough-Elec/Plmb/HVAC 9/2/2021 Approved TIMOTHY MCCURDY
Special/Order Compliance 9/2/2021 Partial Inspection PIERRE VEGA
Wood Frame 9/2/2021 Approved TIMOTHY MCCURDY
Insulation 9/16/2021 Approved ALFREDO BALANDRA
Shower Pan 9/16/2021 Approved ALFREDO BALANDRA
Interior/Exterior Lathing 9/21/2021 Approved ALFREDO BALANDRA
Drywall Nailing 10/21/2021 Approved ALFREDO BALANDRA
Special/Order Compliance 10/21/2021 Partial Inspection PIERRE VEGA
BUILDING-Rough-Frame 5/6/2022 No Access for Inspection ALFREDO BALANDRA
Final 5/6/2022 No Access for Inspection ALFREDO BALANDRA
Smoke Detectors 5/6/2022 No Access for Inspection ALFREDO BALANDRA
BUILDING-Rough-Frame 6/17/2022 Not Ready for Inspection ALFREDO BALANDRA
Final 6/17/2022 Not Ready for Inspection ALFREDO BALANDRA
Smoke Detectors 6/17/2022 Not Ready for Inspection ALFREDO BALANDRA
BUILDING-Rough-Frame 7/11/2022 Not Ready for Inspection ROBERT MINASSIANS
Final 7/11/2022 Corrections Issued ROBERT MINASSIANS
Smoke Detectors 7/11/2022 Not Ready for Inspection ROBERT MINASSIANS
BUILDING-Rough-Frame 8/4/2022 Approved ROBERT MINASSIANS
Final 8/4/2022 Partial Inspection ROBERT MINASSIANS
Smoke Detectors 8/4/2022 Approved ROBERT MINASSIANS
Final 8/17/2022 Conditional Approval ROBERT MINASSIANS
Special/Order Compliance 8/17/2022 Approved COREY HUPP
Final 10/5/2022 Corrections Issued ROBERT CHAVEZ
Final 11/3/2022 OK to Issue CofO COREY HUPP