973 S WILTON PL 90019

Certificate Information: 973 S WILTON PL 90019

Application / Permit
18016-10000-41202
Plan Check / Job No.
B18LA27836
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LABC CH 93. INSTALL STEEL MOMENT FRAMES AND PLYWOOD SHEARWALL.
Permit Issued
Issued on 11/5/2020
Issuing Office
Metro
Current Status
CofC Issued on 12/24/2025

Permit Application Status History

Submitted 12/28/2018 APPLICANT
Assigned to Plan Check Engineer 1/24/2019 MANUEL MONTUFAR
Corrections Issued 1/28/2019 MANUEL MONTUFAR
Quality Review Completed 1/29/2019 HANS SANTIAGO
Building Plans Picked Up 2/4/2019 APPLICANT
Applicant returned to address corrections 10/24/2019 MANUEL MONTUFAR
Plan Check Approved 1/23/2020 MANUEL MONTUFAR
Issued 11/5/2020 APPLICANT
OK for CofC 12/19/2025 DARRYL ARNOLD
CofC Issued 12/24/2025 ERNESTO CORRAL

Permit Application Clearance Information

HPOZ Cleared 9/16/2019 BRADLEY FURUYA
Housing rent stabilization Cleared 9/30/2020 STEVEN HOFSTAD
Hold Cleared 12/4/2020 JASON SHEETS

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/9/2020 Conditional Approval DARRYL ARNOLD
Pre-Inspection 12/7/2020 Approved DARRYL ARNOLD
Footing/Foundation/Slab 12/9/2020 Approved DARRYL ARNOLD
Deputy Steel/Welding 12/11/2020 Conditional Approval JONATHAN QUACH
Deputy Drilled-In Anchors 1/13/2021 Conditional Approval MARK FERRARI
Deputy Reinf. Concrete 1/19/2021 Conditional Approval JONATHAN QUACH
Reinforced Concrete Frame 1/19/2021 Not Ready for Inspection JONATHAN QUACH
Structural Steel Frame 1/19/2021 Not Ready for Inspection JONATHAN QUACH
Reinforced Concrete Frame 1/20/2021 Corrections Issued MARK FERRARI
Structural Steel Frame 1/20/2021 Corrections Issued MARK FERRARI
Footing/Foundation/Slab 6/30/2021 Partial Inspection MARK FERRARI
Footing/Foundation/Slab 7/1/2021 Corrections Issued MARK FERRARI
Footing/Foundation/Slab 7/6/2021 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Concrete 7/7/2021 Conditional Approval MARK FERRARI
Wood Frame 12/8/2021 Approved DARRYL ARNOLD
Deputy Reinf. Concrete 12/10/2021 Conditional Approval DARRYL ARNOLD
Wall Anchors 4/25/2022 Conditional Approval DARRYL ARNOLD
Wood Frame 4/25/2022 Conditional Approval DARRYL ARNOLD
Wood Frame 6/13/2022 Corrections Issued DARRYL ARNOLD
Deputy Drilled-In Anchors 6/22/2022 Conditional Approval BRUCE CAMPBELL
Wood Frame 6/28/2022 Conditional Approval DARRYL ARNOLD
Final 9/26/2022 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 9/26/2022 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 9/26/2022 Corrections Issued DARRYL ARNOLD
Final 3/16/2023 Corrections Issued DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 3/16/2023 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 3/16/2023 Conditional Approval DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 10/15/2024 Corrections Issued DARRYL ARNOLD
Final 4/4/2025 Not Ready for Inspection DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 4/4/2025 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 4/4/2025 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 4/4/2025 Corrections Issued DARRYL ARNOLD
Final 10/16/2025 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 10/16/2025 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 10/16/2025 Not Ready for Inspection DARRYL ARNOLD
Final 10/17/2025 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 10/17/2025 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 10/17/2025 Corrections Issued DARRYL ARNOLD
Final 12/19/2025 OK for CofC DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 12/19/2025 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 12/19/2025 Approved DARRYL ARNOLD