5359 E VALLEY BLVD 90032

Certificate Information: 5359 E VALLEY BLVD 90032

Application / Permit
18016-10000-40987
Plan Check / Job No.
B18LA27654
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Nursery plant
Work Description
FOR CHANGE OF USE TO INDOOR NURSERY, MANUFACTURING , WAREHOUSE, AND TENANT IMPROVEMENT INSIDE EXISTING WAREHOUSE. 34,246 SF. STATE ENTERPRISE ZONE; NO CHANGE IN PARKING.
Permit Issued
Issued on 7/2/2019
Issuing Office
Metro
Current Status
CofO Issued on 6/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2018 APPLICANT
Assigned to Plan Check Engineer 1/10/2019 STANLEY RAAP
Corrections Issued 1/15/2019 STANLEY RAAP
Quality Review Completed 1/17/2019 FELIX FIGUEROA
Disabled Access Plans Picked Up 1/17/2019 APPLICANT
Building Plans Picked Up 1/25/2019 APPLICANT
Plan Check Approved 3/15/2019 STANLEY RAAP
Issued 7/2/2019 LADBS
Permit Closed-Status Void 2/27/2020 DAVID TSAU
Re-Activate Permit 2/17/2021 DAVID TSAU
TCO Issued (Expire Date: 05-28-2024) 11/30/2023 ERNESTO CORRAL
CofO in Progress 6/14/2024 RONALD JIMENEZ
CofO Issued 6/18/2024 ERNESTO CORRAL
Permit Finaled 6/18/2024 ERNESTO CORRAL

Permit Application Clearance Information

ZA Case Cleared 1/29/2019 MOTOUMI SASAKI
ZA Case Cleared 1/29/2019 MOTOUMI SASAKI
ZI Cleared 1/29/2019 MOTOUMI SASAKI
Eng Process Fee Ord 176,300 Cleared 1/30/2019 ROBYN STEELE
Sewer availability Cleared 1/30/2019 ROBYN STEELE
Project located in CRA area Cleared 2/5/2019 JIM URQUHART
DAS Clearance Cleared 2/12/2019 SHINE LIN
Fire Marshall Fire Life Safety Cleared 3/7/2019 VIDAL GARCIA
Miscellaneous Cleared 3/7/2019 VIDAL GARCIA

Contact Information

Contractor Fortis 3 Construction Inc; Lic. No.: 936140-B 2383 CARLTON PLACE UNIT A      COSTA MESA, CA 92627
Engineer Li,, Dacheng David; Lic. No.: C58075 3129 S HACIENDA BL STE 524      HACIENDA HEIGHTS, CA 91745

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/8/2019 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 7/22/2019 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 8/8/2019 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 8/8/2019 Partial Inspection JEFFREY FULTON
Structural Steel Frame 9/11/2019 Partial Inspection JEFFREY FULTON
Wood Frame 10/16/2019 Partial Inspection JEFFREY FULTON
Special/Order Compliance 2/27/2020 Partial Inspection RONALD PACHECO
Light Gage Steel Frame 11/2/2022 Partial Approval MARK FERRARI
Structural Steel Frame 11/2/2022 Partial Approval MARK FERRARI
Drywall Nailing 11/22/2022 Partial Approval MARK FERRARI
Drywall Nailing 3/6/2023 Not Ready for Inspection VAHE KELEDJIAN
Final 3/6/2023 Not Ready for Inspection VAHE KELEDJIAN
Pre-Inspection 3/6/2023 Approved VAHE KELEDJIAN
SGSOV-Seismic Gas S/O Valve 3/6/2023 SGSOV Not Ready VAHE KELEDJIAN
Smoke Detectors 3/6/2023 Not Ready for Inspection VAHE KELEDJIAN
Structural Steel Frame 3/6/2023 Not Ready for Inspection VAHE KELEDJIAN
Pre-Inspection 9/22/2023 Not Ready for Inspection JULIAN CAPUCETTI
Drywall Nailing 10/13/2023 Approved RONALD JIMENEZ
Final 10/13/2023 Not Ready for Inspection RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 10/13/2023 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 10/13/2023 Approved RONALD JIMENEZ
Structural Steel Frame 10/13/2023 Approved RONALD JIMENEZ
Special/Order Compliance 11/16/2023 Not Ready for Inspection JEROME BLACKWOOD
Final 11/22/2023 Partial Inspection KATY RAMIREZ
Final 11/28/2023 Partial Inspection KATY RAMIREZ
Final 3/20/2024 Conditional Approval RONALD JIMENEZ
Final 4/8/2024 Conditional Approval RONALD JIMENEZ
Special/Order Compliance 5/1/2024 Approved RONALD JIMENEZ
Final 6/14/2024 OK to Issue CofO RONALD JIMENEZ