415-421 S ST ANDREWS PL 90020
Certificate Information: 415-421 S ST ANDREWS PL 90020
- Application / Permit
- 18016-10000-40945
- Plan Check / Job No.
- B18LA27597
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL 8 STEEL CANTILEVER COLUMN
- Permit Issued
- Issued on 2/24/2022
- Issuing Office
- Current Status
- CofC Issued on 9/27/2022
Permit Application Status History
| Submitted | 12/24/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2019 | JAIME OROZCO |
| Corrections Issued | 2/5/2019 | JAIME OROZCO |
| Quality Review Completed | 2/8/2019 | HANS SANTIAGO |
| Plan Check Approved | 12/20/2019 | MANUEL MONTUFAR |
| Plan Check Approved | 12/20/2019 | JESSE VIDUYA |
| Plan Check Approved | 11/22/2021 | JESSE VIDUYA |
| Issued | 2/24/2022 | APPLICANT |
| Building Plans Picked Up | 3/1/2022 | APPLICANT |
| OK for CofC | 9/21/2022 | DARRYL ARNOLD |
| CofC Issued | 9/27/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 12/27/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Cha Kyungmin; Lic. No.: 1018067-B | 917 S NEW HAMPSHIRE AVENUE 103 LOS ANGELES, CA 90006 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/18/2022 | Approved | BRUCE CAMPBELL |
| Footing/Foundation/Slab | 4/11/2022 | Approved | DARRYL ARNOLD |
| Footing/Foundation/Slab | 5/9/2022 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 6/3/2022 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Steel/Welding | 6/3/2022 | Conditional Approval | BRUCE CAMPBELL |
| Structural Steel Frame | 6/22/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 6/27/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 7/7/2022 | Approved | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 7/21/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 7/22/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 9/21/2022 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 9/21/2022 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 9/21/2022 | Approved | DARRYL ARNOLD |