3844 S POTOMAC AVE 90008
Certificate Information: 3844 S POTOMAC AVE 90008
- Application / Permit
- 18016-10000-40341
- Plan Check / Job No.
- B18LA27125
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93 USING MF AND SCCS.
- Permit Issued
- Issued on 2/8/2021
- Issuing Office
- Current Status
- CofC Issued on 12/14/2022
Permit Application Status History
| Submitted | 12/18/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/17/2019 | DANIEL SANJUAN |
| Corrections Issued | 1/23/2019 | DANIEL SANJUAN |
| Quality Review Completed | 1/25/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 2/13/2019 | APPLICANT |
| Plan Check Approved | 2/19/2019 | DANIEL SANJUAN |
| Issued | 2/8/2021 | APPLICANT |
| OK for CofC | 5/5/2021 | DARRYL ARNOLD |
| CofC Issued | 12/14/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 10/13/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang, Yuan Ni; Lic. No.: C68149 | , |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/2/2021 | Approved | DARRYL ARNOLD |
| Deputy Steel/Welding | 3/9/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 3/10/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 3/11/2021 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 3/15/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 3/16/2021 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 3/19/2021 | Conditional Approval | MARK FERRARI |
| Wood Frame | 3/26/2021 | Corrections Issued | MARK FERRARI |
| Wood Frame | 4/1/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Drywall Nailing | 4/7/2021 | Corrections Issued | DARRYL ARNOLD |
| Interior/Exterior Lathing | 4/7/2021 | Conditional Approval | DARRYL ARNOLD |
| Final | 5/5/2021 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 5/5/2021 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 5/5/2021 | Approved | DARRYL ARNOLD |
| Special/Order Compliance | 11/10/2022 | Corrections Issued | DARRYL ARNOLD |