520 N HAYWORTH AVE 90048
Certificate Information: 520 N HAYWORTH AVE 90048
- Application / Permit
- 18016-10000-39951
- Plan Check / Job No.
- B18LA26842
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY SEISMIC RETROFIT PER LABC Chapter 93: 1 SCCS AND SHEAR WALLS
- Permit Issued
- Issued on 4/20/2020
- Issuing Office
- Current Status
- CofC Issued on 1/11/2021
Permit Application Status History
| Submitted | 12/13/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/27/2018 | DANIEL SANJUAN |
| Corrections Issued | 1/10/2019 | DANIEL SANJUAN |
| Quality Review Completed | 1/11/2019 | HANS SANTIAGO |
| Plan Check Approved | 8/23/2019 | DANIEL SANJUAN |
| Issued | 4/20/2020 | APPLICANT |
| OK for CofC | 1/8/2021 | MARK FERRARI |
| OK to Issue CofC | 1/8/2021 | ERNESTO CORRAL |
| CofC Issued | 1/11/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 1/13/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Quakestrong; Lic. No.: 1037437-B | 1213 LA BREA AVENUE LOS ANGELES, CA 90019 |
| Engineer | Alexander,, Andy Joseph; Lic. No.: C84086 | 1730 E HOLLY AVE STE 107 EL SEGUNDO, CA 90245 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 5/6/2020 | No Access for Inspection | FELIX CEBALLOS |
| Pre-Inspection | 5/8/2020 | Approved | FELIX CEBALLOS |
| Deputy Reinf. Concrete | 7/27/2020 | Partial Approval | FELIX CEBALLOS |
| Deputy Drilled-In Anchors | 7/28/2020 | Conditional Approval | VAHE KELEDJIAN |
| Deputy Steel/Welding | 7/30/2020 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 8/6/2020 | Corrections Issued | VAHE KELEDJIAN |
| Structural Steel Frame | 8/6/2020 | Not Ready for Inspection | VAHE KELEDJIAN |
| Wood Frame | 8/6/2020 | Not Ready for Inspection | VAHE KELEDJIAN |
| Deputy Steel/Welding | 8/28/2020 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 9/3/2020 | Approved | DANIEL COLLINS |
| Structural Steel Frame | 9/3/2020 | Approved | DANIEL COLLINS |
| Wood Frame | 9/3/2020 | Not Ready for Inspection | DANIEL COLLINS |
| Wood Frame | 9/4/2020 | Approved | DANIEL COLLINS |
| Deputy Reinf. Concrete | 9/8/2020 | Conditional Approval | MARK FERRARI |
| Interior/Exterior Lathing | 9/14/2020 | Approved | DARRYL ARNOLD |
| Final | 9/24/2020 | Conditional Approval | MARK FERRARI |
| METHANE-Final | 9/24/2020 | Approved | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 9/24/2020 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 9/24/2020 | Approved | MARK FERRARI |
| Final | 1/8/2021 | OK for CofC | MARK FERRARI |