520 N HAYWORTH AVE 90048

Certificate Information: 520 N HAYWORTH AVE 90048

Application / Permit
18016-10000-39951
Plan Check / Job No.
B18LA26842
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT-STORY SEISMIC RETROFIT PER LABC Chapter 93: 1 SCCS AND SHEAR WALLS
Permit Issued
Issued on 4/20/2020
Issuing Office
Current Status
CofC Issued on 1/11/2021

Permit Application Status History

Submitted 12/13/2018 APPLICANT
Assigned to Plan Check Engineer 12/27/2018 DANIEL SANJUAN
Corrections Issued 1/10/2019 DANIEL SANJUAN
Quality Review Completed 1/11/2019 HANS SANTIAGO
Plan Check Approved 8/23/2019 DANIEL SANJUAN
Issued 4/20/2020 APPLICANT
OK for CofC 1/8/2021 MARK FERRARI
OK to Issue CofC 1/8/2021 ERNESTO CORRAL
CofC Issued 1/11/2021 ERNESTO CORRAL

Permit Application Clearance Information

Housing rent stabilization Cleared 1/13/2020 PHILLIP MUNGUIA

Contact Information

Contractor Quakestrong; Lic. No.: 1037437-B 1213 LA BREA AVENUE      LOS ANGELES, CA 90019
Engineer Alexander,, Andy Joseph; Lic. No.: C84086 1730 E HOLLY AVE STE 107      EL SEGUNDO, CA 90245

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 5/6/2020 No Access for Inspection FELIX CEBALLOS
Pre-Inspection 5/8/2020 Approved FELIX CEBALLOS
Deputy Reinf. Concrete 7/27/2020 Partial Approval FELIX CEBALLOS
Deputy Drilled-In Anchors 7/28/2020 Conditional Approval VAHE KELEDJIAN
Deputy Steel/Welding 7/30/2020 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 8/6/2020 Corrections Issued VAHE KELEDJIAN
Structural Steel Frame 8/6/2020 Not Ready for Inspection VAHE KELEDJIAN
Wood Frame 8/6/2020 Not Ready for Inspection VAHE KELEDJIAN
Deputy Steel/Welding 8/28/2020 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 9/3/2020 Approved DANIEL COLLINS
Structural Steel Frame 9/3/2020 Approved DANIEL COLLINS
Wood Frame 9/3/2020 Not Ready for Inspection DANIEL COLLINS
Wood Frame 9/4/2020 Approved DANIEL COLLINS
Deputy Reinf. Concrete 9/8/2020 Conditional Approval MARK FERRARI
Interior/Exterior Lathing 9/14/2020 Approved DARRYL ARNOLD
Final 9/24/2020 Conditional Approval MARK FERRARI
METHANE-Final 9/24/2020 Approved MARK FERRARI
SGSOV-Seismic Gas S/O Valve 9/24/2020 SGSOV Approved MARK FERRARI
Smoke Detectors 9/24/2020 Approved MARK FERRARI
Final 1/8/2021 OK for CofC MARK FERRARI