263 W 15TH ST 90731
Certificate Information: 263 W 15TH ST 90731
- Application / Permit
- 18016-10000-39925
- Plan Check / Job No.
- B18LA26823
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93 USING 1 NEW STEEL MOMENT FRAME.
- Permit Issued
- Issued on 1/21/2022
- Issuing Office
- Current Status
- CofC Issued on 4/19/2022
Permit Application Status History
| Submitted | 12/13/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2019 | HANS SANTIAGO |
| Corrections Issued | 1/14/2019 | HANS SANTIAGO |
| Quality Review Completed | 1/14/2019 | SAI KHUM |
| Plan Check Approved | 2/13/2019 | Andrew Santiago |
| Issued | 1/21/2022 | APPLICANT |
| Building Plans Picked Up | 1/25/2022 | APPLICANT |
| OK for CofC | 4/4/2022 | JOEY BUCHANAN |
| CofC Issued | 4/19/2022 | DAVID TSAU |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 1/19/2022 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Zebra Construction Inc; Lic. No.: 1055609-B | 145 S FAIRFAX STE 200/300 LOS ANGELES, CA 90036 |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 2/3/2022 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 2/7/2022 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 2/16/2022 | Approved | JOEY BUCHANAN |
| Structural Steel Frame | 2/16/2022 | Approved | JOEY BUCHANAN |
| Wood Frame | 2/16/2022 | Approved | JOEY BUCHANAN |
| Drywall Nailing | 2/23/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 2/23/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 3/8/2022 | No Access for Inspection | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 3/8/2022 | SGSOV Not Ready | JOEY BUCHANAN |
| Smoke Detectors | 3/8/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Final | 3/10/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 3/10/2022 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 3/10/2022 | Approved | JOEY BUCHANAN |
| Final | 3/30/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Final | 4/4/2022 | OK for CofC | JOEY BUCHANAN |