3210 N PASADENA AVE 90031
Certificate Information: 3210 N PASADENA AVE 90031
- Application / Permit
- 18016-10000-39841
- Plan Check / Job No.
- B18LA26756
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL TWO (N) SCCS
- Permit Issued
- Issued on 1/16/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 2/16/2021
Permit Application Status History
| Submitted | 12/13/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/17/2019 | DEAN RYAN REYES |
| Corrections Issued | 1/22/2019 | DEAN RYAN REYES |
| Quality Review Completed | 1/23/2019 | SAI KHUM |
| Building Plans Picked Up | 1/28/2019 | APPLICANT |
| Plan Check Approved | 9/13/2019 | DEAN RYAN REYES |
| Issued | 1/16/2020 | LADBS |
| OK for CofC | 2/16/2021 | MARK FERRARI |
| CofC Issued | 2/16/2021 | DAVID TSAU |
Permit Application Clearance Information
| HPOZ | Cleared | 5/31/2019 | JONATHAN KAPLAN |
| ZI | Cleared | 5/31/2019 | JONATHAN KAPLAN |
| Housing rent stabilization | Cleared | 12/4/2019 | STEVEN HOFSTAD |
Contact Information
| Contractor | Pacific West Construction Services Inc; Lic. No.: 985970-B | 1601 PACIFIC COAST HWY STE 160 HERMOSA BEACH, CA 90254 |
| Engineer | Farmand, Anthony E; Lic. No.: C62595 | 4675 MACARTHUR COURT SUITE 800 NEWPORT BEACH, CA 92660 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/7/2020 | Corrections Issued | MARK FERRARI |
| Deputy Drilled-In Anchors | 7/9/2020 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 7/9/2020 | Conditional Approval | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 7/13/2020 | Corrections Issued | MARK FERRARI |
| Footing/Foundation/Slab | 7/13/2020 | Not Ready for Inspection | MARK FERRARI |
| Structural Steel Frame | 7/13/2020 | Not Ready for Inspection | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 7/31/2020 | Corrections Issued | VAHE KELEDJIAN |
| Footing/Foundation/Slab | 7/31/2020 | Not Ready for Inspection | VAHE KELEDJIAN |
| Structural Steel Frame | 7/31/2020 | Not Ready for Inspection | VAHE KELEDJIAN |
| Wood Frame | 7/31/2020 | Not Ready for Inspection | VAHE KELEDJIAN |
| Excavation/Setback/Form/Re-Bar | 8/3/2020 | Partial Inspection | MARK FERRARI |
| Footing/Foundation/Slab | 10/26/2020 | Conditional Approval | MARK FERRARI |
| Wood Frame | 10/26/2020 | Not Ready for Inspection | MARK FERRARI |
| Deputy Reinf. Concrete | 10/29/2020 | Conditional Approval | MARK FERRARI |
| Wood Frame | 11/5/2020 | No Access for Inspection | MARK FERRARI |
| Wood Frame | 11/9/2020 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 11/20/2020 | Corrections Issued | MARK FERRARI |
| Wood Frame | 11/24/2020 | Not Ready for Inspection | MARK FERRARI |
| Interior/Exterior Lathing | 12/15/2020 | Corrections Issued | MARK FERRARI |
| Final | 12/31/2020 | Corrections Issued | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 12/31/2020 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 12/31/2020 | Approved | MARK FERRARI |
| Final | 2/16/2021 | OK for CofC | MARK FERRARI |