2332 S BENTLEY AVE 90064

Certificate Information: 2332 S BENTLEY AVE 90064

Application / Permit
18016-10000-39322
Plan Check / Job No.
B18LA26346
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL (N) SCCS.
Permit Issued
Issued on 7/12/2021
Issuing Office
Current Status
CofC Issued on 11/9/2021

Permit Application Status History

Submitted 12/7/2018 APPLICANT
Assigned to Plan Check Engineer 1/3/2019 VARAND SARKISIAN
Corrections Issued 1/7/2019 VARAND SARKISIAN
Quality Review Completed 1/7/2019 HANS SANTIAGO
Building Plans Picked Up 1/17/2019 APPLICANT
Plan Check Approved 2/26/2019 VARAND SARKISIAN
No Progress 9/11/2020 VARAND SARKISIAN
Plan Check Approved 9/11/2020 VARAND SARKISIAN
Issued 7/12/2021 APPLICANT
OK for CofC 10/27/2021 GRANT WOODS
CofC Issued 11/9/2021 DAVID TSAU

Permit Application Clearance Information

Housing rent stabilization Cleared 7/7/2021 PHILLIP MUNGUIA

Contact Information

Contractor Retrofit 1; Lic. No.: 1003868-B 19326 VENTURA BLVD STE 200      TARZANA, CA 91356
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/10/2021 Approved GRANT WOODS
Footing/Foundation/Slab 9/1/2021 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 9/7/2021 Conditional Approval GRANT WOODS
Footing/Foundation/Slab 9/10/2021 Partial Approval PAUL DAVIDSON
Wood Frame 9/10/2021 Not Ready for Inspection PAUL DAVIDSON
Deputy Steel/Welding 9/13/2021 Conditional Approval PAUL DAVIDSON
Deputy Wood Construction 9/13/2021 Conditional Approval PAUL DAVIDSON
Wood Frame 9/13/2021 Partial Approval PAUL DAVIDSON
Deputy Steel/Welding 9/14/2021 Conditional Approval PAUL DAVIDSON
Deputy Wood Construction 9/14/2021 Conditional Approval PAUL DAVIDSON
Deputy Drilled-In Anchors 9/16/2021 Conditional Approval GRANT WOODS
Deputy Wood Construction 9/16/2021 Conditional Approval PAUL DAVIDSON
Footing/Foundation/Slab 9/16/2021 Approved JOHN DODGE
Structural Steel Frame 9/16/2021 Approved JOHN DODGE
Wood Frame 9/16/2021 Not Ready for Inspection JOHN DODGE
Deputy Reinf. Concrete 9/17/2021 Conditional Approval PAUL DAVIDSON
Structural Steel Frame 9/17/2021 Approved PAUL DAVIDSON
Wood Frame 9/17/2021 Approved PAUL DAVIDSON
Interior/Exterior Lathing 9/27/2021 Approved PAUL DAVIDSON
Final 10/27/2021 OK for CofC GRANT WOODS
SGSOV-Seismic Gas S/O Valve 10/27/2021 SGSOV Approved GRANT WOODS
Smoke Detectors 10/27/2021 Approved GRANT WOODS
Final 11/3/2021 Conditional Approval GRANT WOODS