12945 W OXNARD ST 91401
Certificate Information: 12945 W OXNARD ST 91401
- Application / Permit
- 18016-10000-39278
- Plan Check / Job No.
- B18LA26314
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL 4 (N) SCCS.
- Permit Issued
- Issued on 5/5/2021
- Issuing Office
- Current Status
- CofC Issued on 8/9/2023
Permit Application Status History
| Submitted | 12/7/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/17/2019 | JAIME OROZCO |
| Corrections Issued | 1/23/2019 | JAIME OROZCO |
| Quality Review Completed | 1/28/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 1/29/2019 | APPLICANT |
| Applicant returned to address corrections | 2/7/2019 | JAIME OROZCO |
| Plan Check Approved | 2/15/2019 | JAIME OROZCO |
| Issued | 5/5/2021 | APPLICANT |
| OK for CofC | 6/27/2023 | KENNETH ROBERTS |
| CofC Issued | 8/9/2023 | RICKEY JACKSON |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 4/29/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Ces4; Lic. No.: 1042127-B | 19562 VENTURA BLVD UNIT 238 TARZANA, CA 91356 |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 21201 KITTRIDGE ST APT 9105 WOODLAND HILLS, CA 91303 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 7/12/2021 | No Access for Inspection | JOE VELASQUEZ |
| Pre-Inspection | 7/15/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 8/12/2021 | Corrections Issued | JOE VELASQUEZ |
| Wood Frame | 8/12/2021 | Corrections Issued | JOE VELASQUEZ |
| Wood Frame | 9/15/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/20/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/24/2021 | Partial Approval | JOE VELASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2021 | Partial Approval | KENNETH ROBERTS |
| Footing/Foundation/Slab | 10/26/2021 | Partial Approval | KENNETH ROBERTS |
| Excavation/Setback/Form/Re-Bar | 11/1/2021 | Corrections Issued | KENNETH ROBERTS |
| Excavation/Setback/Form/Re-Bar | 11/9/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 11/9/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 11/10/2021 | Approved | KENNETH ROBERTS |
| Deputy Reinf. Concrete | 11/15/2021 | No Access for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 11/16/2021 | Approved | JOE VELASQUEZ |
| Final | 12/8/2021 | Corrections Issued | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 12/8/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 12/8/2021 | Approved | KENNETH ROBERTS |
| Final | 6/27/2023 | OK for CofC | KENNETH ROBERTS |