3649 S GLENDON AVE 90034
Certificate Information: 3649 S GLENDON AVE 90034
- Application / Permit
- 18016-10000-38961
- Plan Check / Job No.
- B18LA26048
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Multi Family
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93 TO AN (E) CONDOMINIUM BLDG. USING STEEL CANTILEVER COLUMNS & WOOD SHEAR WALLS
- Permit Issued
- Issued on 1/3/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 1/21/2021
Permit Application Status History
| Submitted | 12/4/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2019 | HANS SANTIAGO |
| Corrections Issued | 1/7/2019 | HANS SANTIAGO |
| Quality Review Completed | 1/8/2019 | SAI KHUM |
| Building Plans Picked Up | 1/10/2019 | APPLICANT |
| Plan Check Approved | 3/4/2019 | Andrew Santiago |
| Issued | 1/3/2020 | LADBS |
| OK for CofC | 1/20/2021 | GRANT WOODS |
| CofC Issued | 1/21/2021 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 10/31/2019 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | Demers,, Joe Alan; Lic. No.: C71535 | 1626 S MAYFLOWER AVE UNIT B MONROVIA, CA 91016 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/15/2020 | Partial Inspection | SORIN CIRSTOIU |
| Deputy Steel/Welding | 1/23/2020 | Approved | JEFF BYTHEWAY |
| Deputy Drilled-In Anchors | 1/28/2020 | Conditional Approval | PAUL DAVIDSON |
| Pre-Inspection | 1/28/2020 | Approved | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 1/29/2020 | Approved | PAUL DAVIDSON |
| Wall Anchors | 2/11/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Wood Frame | 2/11/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Insulation | 2/13/2020 | Partial Approval | SORIN CIRSTOIU |
| Wall Anchors | 2/13/2020 | Partial Approval | SORIN CIRSTOIU |
| Interior/Exterior Lathing | 4/2/2020 | Corrections Issued | PAUL DAVIDSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2020 | Approved | GRANT WOODS |
| Interior/Exterior Lathing | 4/17/2020 | Not Ready for Inspection | GRANT WOODS |
| Interior/Exterior Lathing | 4/20/2020 | Approved | GRANT WOODS |
| Final | 1/20/2021 | OK for CofC | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 1/20/2021 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 1/20/2021 | Approved | GRANT WOODS |