822 1/2 S WELLESLEY AVE 90049

Certificate Information: 822 1/2 S WELLESLEY AVE 90049

Application / Permit
18016-10000-38849
Plan Check / Job No.
B18LA25960
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT 20'-3" X 27'-9" REC ROOM TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 4/5/2021
Issuing Office
Current Status
CofO Issued on 10/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2018 APPLICANT
Assigned to Plan Check Engineer 12/20/2018 MICHAEL PEREZ
Corrections Issued 12/26/2018 MICHAEL PEREZ
Quality Review Completed 12/26/2018 SIAVOSH POURSABAHIAN
Building Plans Picked Up 2/7/2019 APPLICANT
Disabled Access Plans Picked Up 7/11/2019 APPLICANT
Plan Check Approved 3/23/2021 MICHAEL PEREZ
Issued 4/5/2021 APPLICANT
CofO in Progress 9/15/2023 CHRISTOPHER WILSON
CofO in Progress 9/15/2023 CHRISTOPHER WILSON
Permit Finaled 10/7/2023 DANIEL ORRANTE
CofO Issued 10/7/2023 DANIEL ORRANTE
Permit Finaled 10/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

CPC Cleared 2/12/2019 SARAH GOLDMAN
ZA Case Cleared 2/12/2019 SARAH GOLDMAN
DAS Clearance Cleared 7/5/2019 SHINE LIN
Address approval Cleared 7/19/2019 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 7/19/2019 ELENA LOPEZ
Housing rent stabilization Cleared 7/19/2019 MICHAEL SOTO
Sewer availability Cleared 7/19/2019 ELENA LOPEZ
Miscellaneous Cleared 11/18/2020 AIDA KARAPETIAN
Unpermitted Dwelling Unit Cleared 11/18/2020 ANACANY HURTADO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/16/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Pre-Inspection 4/23/2021 Partial Inspection KENNETH NAGLE
SGSOV-Seismic Gas S/O Valve 4/23/2021 SGSOV Not Ready KENNETH NAGLE
Special/Order Compliance 4/28/2021 Corrections Issued KENNETH NAGLE
Pre-Inspection 4/27/2022 Partial Inspection JUAN VALENZUELA
Wood Frame 7/22/2022 Corrections Issued STEPHANIE SWANSON
Wood Frame 2/28/2023 Corrections Issued CLAYTON GRAHAM
Wood Frame 3/23/2023 Corrections Issued CLAYTON GRAHAM
Wood Frame 4/25/2023 Approved JESUS PINEDA
Insulation 5/31/2023 Approved JESUS PINEDA
Drywall Nailing 6/6/2023 Approved JESUS PINEDA
Final 8/22/2023 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 8/22/2023 SGSOV Not Ready JESUS PINEDA
Final 9/12/2023 OK to Issue CofO CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 9/12/2023 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 9/12/2023 Approved CHRISTOPHER WILSON