1545 N WILCOX AVE 90028

Certificate Information: 1545 N WILCOX AVE 90028

Application / Permit
18016-10000-38822
Plan Check / Job No.
B18LA25944
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
CHANGE OF USE FROM OFFICE BUILDING TO CORE AND SHELL RESTAURANCT 1ST FLOOR AND CORE SHELL BANQUET HALL ON 2ND FLOOR AND BASEMENT STORAGE. STRUCTURAL UPGRADE TO EXISTING BUILDING COMPLY W/ CH 16.
Permit Issued
Issued on 9/11/2019
Issuing Office
Metro
Current Status
CofO Issued on 12/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2018 APPLICANT
Green Plans Picked Up 12/10/2018 APPLICANT
Disabled Access Plans Picked Up 12/13/2018 APPLICANT
Assigned to Plan Check Engineer 12/27/2018 HERNAN ARREOLA
Corrections Issued 1/17/2019 HERNAN ARREOLA
Quality Review Completed 2/5/2019 BILL STUTSMAN
Building Plans Picked Up 2/5/2019 APPLICANT
Applicant returned to address corrections 4/1/2019 HERNAN ARREOLA
Applicant returned to address corrections 4/15/2019 HERNAN ARREOLA
Applicant returned to address corrections 4/18/2019 HERNAN ARREOLA
Applicant returned to address corrections 5/13/2019 HERNAN ARREOLA
Applicant returned to address corrections 6/11/2019 HERNAN ARREOLA
Plan Check Approved 8/19/2019 HERNAN ARREOLA
Issued 9/11/2019 LADBS
CofO in Progress 12/10/2021 SORIN CIRSTOIU
CofO in Progress 12/10/2021 SORIN CIRSTOIU
CofO Issued 12/16/2021 TED RIES
Permit Finaled 12/16/2021 TED RIES

Permit Application Clearance Information

Sewer availability Cleared 2/8/2019 ELAINE LEI
"D" conditions Cleared 2/12/2019 BLAYNE SUTTON-WILLS
Eng Process Fee Ord 176,300 Cleared 2/15/2019 ELENA LOPEZ
Project located in CRA area Cleared 3/1/2019 JIM URQUHART
Green Code Cleared 3/22/2019 COLIN LOREDO
DAS Clearance Cleared 4/22/2019 SHINE LIN
Fire Marshall Fire Life Safety Cleared 6/5/2019 PEJMAN NOORI
Historic monument Cleared 6/17/2019 LAMBERT GIESSINGER

Contact Information

Architect Rockefeller,, Darrell S; Lic. No.: C14927 620 24TH PLACE      HERMOSA BEACH, CA 90254
Contractor Five Chairs Construction; Lic. No.: 488672-B 1605 CAHUENGA BLVD      LOS ANGELES, CA 90028
Engineer Hassan,, Mohamed Ali; Lic. No.: S5285 3621 HARBOR BLVD #125      SANTA ANA, CA 92704

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/26/2020 Partial Inspection LANNY MERRICK
Special/Order Compliance 5/29/2020 Conditional Approval LANNY MERRICK
Footing/Foundation/Slab 6/3/2020 Not Ready for Inspection LANNY MERRICK
Deputy Steel/Welding 6/16/2020 Conditional Approval LANNY MERRICK
Deputy Steel/Welding 6/17/2020 Conditional Approval LANNY MERRICK
Excavation/Setback/Form/Re-Bar 6/17/2020 Corrections Issued LANNY MERRICK
Deputy Steel/Welding 6/18/2020 Conditional Approval LANNY MERRICK
Deputy Steel/Welding 6/19/2020 Conditional Approval LANNY MERRICK
Excavation/Setback/Form/Re-Bar 6/19/2020 Partial Approval LANNY MERRICK
Deputy Steel/Welding 6/22/2020 Conditional Approval LANNY MERRICK
Deputy Steel/Welding 7/7/2020 Conditional Approval RUSSELL BONVOULOIR
Deputy Steel/Welding 7/8/2020 Partial Approval EDWIN GREGORYONA
Green Building Rough 7/8/2020 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 7/8/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 7/9/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 7/14/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 7/15/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 7/16/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 7/17/2020 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 7/17/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 7/20/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 7/24/2020 Conditional Approval RUSSELL BONVOULOIR
Deputy Steel/Welding 7/27/2020 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 7/28/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 7/28/2020 Partial Approval EDWIN GREGORYONA
Green Building Rough 7/28/2020 Partial Inspection EDWIN GREGORYONA
Light Gage Steel Frame 7/28/2020 Partial Approval EDWIN GREGORYONA
Reinforced Concrete Frame 7/28/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 7/29/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 7/30/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 7/31/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 8/3/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 8/4/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 8/5/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 8/6/2020 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 8/7/2020 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 8/7/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 8/7/2020 Conditional Approval RUSSELL BONVOULOIR
Deputy Steel/Welding 8/10/2020 Conditional Approval RUSSELL BONVOULOIR
Deputy Steel/Welding 8/11/2020 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 8/11/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 8/12/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 8/13/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 8/14/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 8/17/2020 Partial Approval EDWIN GREGORYONA
Green Building Rough 8/25/2020 Partial Inspection RUSSELL BONVOULOIR
Reinforced Concrete Frame 8/25/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 9/14/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 9/15/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 9/16/2020 Partial Approval EDWIN GREGORYONA
Reinforced Masonry Frame 9/16/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 9/17/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 9/18/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 9/22/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 9/23/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 9/24/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 9/25/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 9/29/2020 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 9/29/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 9/30/2020 Approved EDWIN GREGORYONA
Deputy Steel/Welding 10/2/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 10/5/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 10/6/2020 Conditional Approval RUSSELL BONVOULOIR
Deputy Steel/Welding 10/7/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 10/8/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 10/9/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 10/13/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 10/14/2020 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 10/14/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 10/15/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 10/16/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 10/19/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 10/20/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 10/21/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 10/22/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 10/23/2020 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 10/23/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 10/26/2020 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 10/28/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 10/28/2020 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 10/29/2020 Conditional Approval RUSSELL BONVOULOIR
Deputy Steel/Welding 10/29/2020 Conditional Approval RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 10/30/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 10/30/2020 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 11/2/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 11/2/2020 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 11/4/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 11/4/2020 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 11/5/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 11/5/2020 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 11/6/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 11/6/2020 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 11/9/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 11/9/2020 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 11/10/2020 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 11/10/2020 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 12/14/2020 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 12/17/2020 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 1/11/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 1/19/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 1/19/2021 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 2/4/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 2/4/2021 Not Ready for Inspection EDWIN GREGORYONA
Light Gage Steel Frame 5/14/2021 Partial Inspection RUSSELL BONVOULOIR
Interior/Exterior Lathing 5/18/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 6/18/2021 Corrections Issued RUSSELL BONVOULOIR
Interior/Exterior Lathing 7/2/2021 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 7/9/2021 Partial Approval JONATHAN QUACH
Drywall Nailing 8/10/2021 Partial Approval DAVID BURKHEAD
Green Building Rough 8/10/2021 Not Ready for Inspection DAVID BURKHEAD
Deputy Fireproofing 8/11/2021 Conditional Approval RUSSELL BONVOULOIR
Drywall Nailing 10/14/2021 Not Ready for Inspection SORIN CIRSTOIU
Final 10/14/2021 Not Ready for Inspection SORIN CIRSTOIU
Green Building Final 10/14/2021 Not Ready for Inspection SORIN CIRSTOIU
Green Building Rough 10/14/2021 Not Ready for Inspection SORIN CIRSTOIU
Reinforced Concrete Frame 10/14/2021 Not Ready for Inspection SORIN CIRSTOIU
Reinforced Masonry Frame 10/14/2021 Not Ready for Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 10/14/2021 SGSOV Approved SORIN CIRSTOIU
Smoke Detectors 10/14/2021 Approved SORIN CIRSTOIU
Structural Steel Frame 10/14/2021 Not Ready for Inspection SORIN CIRSTOIU
Drywall Nailing 10/29/2021 Partial Inspection SORIN CIRSTOIU
Final 10/29/2021 Partial Inspection SORIN CIRSTOIU
Green Building Final 10/29/2021 Partial Inspection SORIN CIRSTOIU
Green Building Rough 10/29/2021 Partial Inspection SORIN CIRSTOIU
Reinforced Concrete Frame 10/29/2021 Partial Inspection SORIN CIRSTOIU
Reinforced Masonry Frame 10/29/2021 Partial Inspection SORIN CIRSTOIU
Structural Steel Frame 10/29/2021 Partial Inspection SORIN CIRSTOIU
Drywall Nailing 12/2/2021 Not Ready for Inspection SORIN CIRSTOIU
Final 12/2/2021 Not Ready for Inspection SORIN CIRSTOIU
Green Building Final 12/2/2021 Not Ready for Inspection SORIN CIRSTOIU
Green Building Rough 12/2/2021 Not Ready for Inspection SORIN CIRSTOIU
Reinforced Concrete Frame 12/2/2021 Not Ready for Inspection SORIN CIRSTOIU
Reinforced Masonry Frame 12/2/2021 Not Ready for Inspection SORIN CIRSTOIU
Structural Steel Frame 12/2/2021 Not Ready for Inspection SORIN CIRSTOIU
Drywall Nailing 12/6/2021 Partial Inspection SORIN CIRSTOIU
Final 12/6/2021 Partial Inspection SORIN CIRSTOIU
Green Building Final 12/6/2021 Approved SORIN CIRSTOIU
Green Building Rough 12/6/2021 Approved SORIN CIRSTOIU
Reinforced Concrete Frame 12/6/2021 Partial Inspection SORIN CIRSTOIU
Reinforced Masonry Frame 12/6/2021 Partial Inspection SORIN CIRSTOIU
Structural Steel Frame 12/6/2021 Partial Inspection SORIN CIRSTOIU
Drywall Nailing 12/10/2021 Approved SORIN CIRSTOIU
Final 12/10/2021 OK to Issue CofO SORIN CIRSTOIU
Reinforced Concrete Frame 12/10/2021 Approved SORIN CIRSTOIU
Reinforced Masonry Frame 12/10/2021 Approved SORIN CIRSTOIU
Structural Steel Frame 12/10/2021 Approved SORIN CIRSTOIU