933 S NORTON AVE 90019

Certificate Information: 933 S NORTON AVE 90019

Application / Permit
18016-10000-38569
Plan Check / Job No.
B18LA25745
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL (1) NEW SCCS .
Permit Issued
Issued on 5/11/2020
Issuing Office
Current Status
CofC Issued on 10/16/2020

Permit Application Status History

Submitted 11/30/2018 APPLICANT
Assigned to Plan Check Engineer 1/10/2019 AUNG SOE
Corrections Issued 1/15/2019 AUNG SOE
Quality Review Completed 1/17/2019 SAI KHUM
Building Plans Picked Up 1/24/2019 APPLICANT
Plan Check Approved 8/27/2019 THOMAS SHERMAN
Issued 5/11/2020 APPLICANT
OK for CofC 10/7/2020 MARK FERRARI
CofC Issued 10/16/2020 ERNESTO CORRAL

Permit Application Clearance Information

HPOZ Cleared 2/20/2019 BRADLEY FURUYA
Housing rent stabilization Cleared 5/4/2020 MICHAEL GREGERSON

Contact Information

Contractor Optimum Seismic Inc; Lic. No.: 1012702-B 5508 S SANTA FE AVENUE      VERNON, CA 90058
Engineer Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 1377 S BEVERLY GLEN BLVD 308      LOS ANGELES, CA 90024

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/20/2020 Corrections Issued DARRYL ARNOLD
Deputy Steel/Welding 6/2/2020 Partial Approval DARRYL ARNOLD
Wood Frame 6/2/2020 Approved DARRYL ARNOLD
Deputy Steel/Welding 6/4/2020 Approved DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 6/4/2020 Approved DARRYL ARNOLD
Footing/Foundation/Slab 6/4/2020 Approved DARRYL ARNOLD
Structural Steel Frame 6/4/2020 Approved DARRYL ARNOLD
Deputy Reinf. Concrete 6/5/2020 Conditional Approval VAHE KELEDJIAN
Interior/Exterior Lathing 6/10/2020 Approved DARRYL ARNOLD
Final 9/17/2020 Conditional Approval MARK FERRARI
METHANE-Final 9/17/2020 Approved MARK FERRARI
SGSOV-Seismic Gas S/O Valve 9/17/2020 SGSOV Approved MARK FERRARI
Smoke Detectors 9/17/2020 Approved MARK FERRARI
Final 10/7/2020 OK for CofC MARK FERRARI