442 N NORMANDIE PL 90004
Certificate Information: 442 N NORMANDIE PL 90004
- Application / Permit
- 18016-10000-38156
- Plan Check / Job No.
- B18LA25408
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL (1) MF AND (1) SHEAR WALL.
- Permit Issued
- Issued on 6/10/2020
- Issuing Office
- Current Status
- CofC Issued on 12/15/2020
Permit Application Status History
| Submitted | 11/28/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2019 | EVERARDO SANTOS |
| Corrections Issued | 1/15/2019 | EVERARDO SANTOS |
| Quality Review Completed | 1/16/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 1/22/2019 | APPLICANT |
| Plan Check Approved | 3/28/2019 | EVERARDO SANTOS |
| Issued | 6/10/2020 | APPLICANT |
| OK for CofC | 12/10/2020 | JONATHAN QUACH |
| CofC Issued | 12/15/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 6/9/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | National Retrofit Service Inc; Lic. No.: 1062123-B | 4456 ALTA CANYADA RD LA CANADA FLINTRIDGE, CA 91011 |
| Engineer | Puliyadi,, Senthilnath Surendran; Lic. No.: C71630 | 114 SHADOWHILL CIRCLE SAN RAMON, CA 94583 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/24/2020 | Conditional Approval | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 6/24/2020 | Partial Approval | MARK FERRARI |
| Pre-Inspection | 6/24/2020 | Approved | MARK FERRARI |
| Deputy Steel/Welding | 6/26/2020 | Partial Approval | FELIX CEBALLOS |
| Deputy Steel/Welding | 7/1/2020 | Partial Approval | FELIX CEBALLOS |
| Footing/Foundation/Slab | 7/1/2020 | Not Ready for Inspection | FELIX CEBALLOS |
| Footing/Foundation/Slab | 7/2/2020 | Corrections Issued | MARK FERRARI |
| Footing/Foundation/Slab | 7/9/2020 | Approved | MARK FERRARI |
| Wood Frame | 7/9/2020 | Not Ready for Inspection | MARK FERRARI |
| Deputy Steel/Welding | 7/13/2020 | Conditional Approval | MARK FERRARI |
| Wood Frame | 9/17/2020 | Not Ready for Inspection | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2020 | Approved | MARK FERRARI |
| Structural Steel Frame | 10/28/2020 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 11/6/2020 | Approved | MARK FERRARI |
| Final | 12/10/2020 | OK for CofC | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 12/10/2020 | SGSOV Approved | JONATHAN QUACH |