247 N CATALINA ST 90004

Certificate Information: 247 N CATALINA ST 90004

Application / Permit
18016-10000-38155
Plan Check / Job No.
B18LA25407
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CH. 93 USING 1 OMF.
Permit Issued
Issued on 6/16/2020
Issuing Office
Current Status
CofC Issued on 3/5/2021

Permit Application Status History

Submitted 11/28/2018 APPLICANT
Assigned to Plan Check Engineer 1/10/2019 EVERARDO SANTOS
Corrections Issued 1/15/2019 EVERARDO SANTOS
Quality Review Completed 1/16/2019 HANS SANTIAGO
Building Plans Picked Up 1/28/2019 APPLICANT
Plan Check Approved 5/31/2019 EVERARDO SANTOS
Issued 6/16/2020 APPLICANT
OK for CofC 3/1/2021 MARK FERRARI
CofC Issued 3/5/2021 ERNESTO CORRAL

Permit Application Clearance Information

Housing rent stabilization Cleared 6/8/2020 ISMAEL HERNANDEZ

Contact Information

Contractor National Retrofit Service Inc; Lic. No.: 1062123-B 4456 ALTA CANYADA RD      LA CANADA FLINTRIDGE, CA 91011
Engineer Puliyadi,, Senthilnath Surendran; Lic. No.: C71630 114 SHADOWHILL CIRCLE      SAN RAMON, CA 94583

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/19/2020 Corrections Issued MARK FERRARI
Footing/Foundation/Slab 6/23/2020 Corrections Issued MARK FERRARI
Pre-Inspection 6/23/2020 Approved MARK FERRARI
Excavation/Setback/Form/Re-Bar 6/24/2020 Corrections Issued MARK FERRARI
Footing/Foundation/Slab 6/24/2020 Not Ready for Inspection MARK FERRARI
Footing/Foundation/Slab 7/24/2020 Approved MARK FERRARI
Deputy Steel/Welding 7/28/2020 Conditional Approval MARK FERRARI
Structural Steel Frame 8/12/2020 Corrections Issued VAHE KELEDJIAN
Wood Frame 8/12/2020 Corrections Issued VAHE KELEDJIAN
Wood Frame 9/24/2020 Not Ready for Inspection MARK FERRARI
Structural Steel Frame 10/8/2020 Approved MARK FERRARI
Wood Frame 10/8/2020 Approved MARK FERRARI
Interior/Exterior Lathing 11/5/2020 Corrections Issued MARK FERRARI
Final 12/10/2020 Partial Inspection JONATHAN QUACH
METHANE-Final 12/10/2020 Approved JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 12/10/2020 SGSOV Approved JONATHAN QUACH
Smoke Detectors 12/10/2020 Approved JONATHAN QUACH
Final 3/1/2021 OK for CofC MARK FERRARI