2140 N ALTA ST 90031

Certificate Information: 2140 N ALTA ST 90031

Application / Permit
18016-10000-38096
Plan Check / Job No.
B18LA25360
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft story retrofit per LAMC Div 93: (4) Special Cantilever Column System
Permit Issued
Issued on 1/4/2021
Issuing Office
Current Status
CofC Issued on 11/1/2021

Permit Application Status History

Submitted 11/27/2018 APPLICANT
Assigned to Plan Check Engineer 1/10/2019 HERNAN ARREOLA
Corrections Issued 1/17/2019 HERNAN ARREOLA
Quality Review Completed 1/18/2019 SAI KHUM
Building Plans Picked Up 1/28/2019 APPLICANT
Plan Check Approved 3/6/2019 HERNAN ARREOLA
No Progress 3/6/2019 HERNAN ARREOLA
Plan Check Approved 5/3/2019 HERNAN ARREOLA
Issued 1/4/2021 APPLICANT
OK for CofC 10/28/2021 MARK FERRARI
CofC Issued 11/1/2021 WINSTON DUNNING

Permit Application Clearance Information

"D" conditions Cleared 6/13/2019 ANNA VAN
"Q" conditions Cleared 6/13/2019 ANNA VAN
Housing rent stabilization Cleared 10/15/2020 MICHAEL SOTO

Contact Information

Contractor Mokhtari Mehrdad; Lic. No.: 836891-B 1557 WESTWOOD BLVD #165      LOS ANGELES, CA 90024
Engineer Cohan,, Behzad Barry; Lic. No.: C36291 321 S PALM DR      BEVERLY HILLS, CA 90212

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/26/2021 Approved MARK FERRARI
Pre-Inspection 2/8/2021 Corrections Issued MARK FERRARI
Wood Frame 2/18/2021 Corrections Issued MARK FERRARI
Wood Frame 2/26/2021 Partial Approval MARK FERRARI
Wood Frame 3/11/2021 Partial Approval MARK FERRARI
Wood Frame 3/18/2021 Partial Approval LANNY MERRICK
Deputy Wood Construction 4/6/2021 Approved MARK FERRARI
Wood Frame 4/6/2021 Partial Approval MARK FERRARI
Deputy Other (see comments) 4/7/2021 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 4/9/2021 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 4/14/2021 Corrections Issued MARK FERRARI
Deputy Steel/Welding 4/23/2021 Conditional Approval MARK FERRARI
Deputy Steel/Welding 4/26/2021 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 5/6/2021 Conditional Approval MARK FERRARI
Deputy Steel/Welding 5/11/2021 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 5/11/2021 Corrections Issued MARK FERRARI
Deputy Steel/Welding 5/12/2021 Conditional Approval MARK FERRARI
Interior/Exterior Lathing 5/17/2021 Partial Approval MARK FERRARI
Footing/Foundation/Slab 5/27/2021 Not Ready for Inspection DARRYL ARNOLD
Deputy Reinf. Concrete 6/2/2021 Conditional Approval MARK FERRARI
Wood Frame 7/12/2021 Not Ready for Inspection MARK FERRARI
Structural Steel Frame 8/16/2021 Approved MARK FERRARI
Wood Frame 8/16/2021 Not Ready for Inspection MARK FERRARI
Wood Frame 8/18/2021 Partial Approval MARK FERRARI
Deputy Wood Construction 8/25/2021 Approved MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 8/25/2021 Approved MARK FERRARI
Interior/Exterior Lathing 9/13/2021 Not Ready for Inspection MARK FERRARI
Interior/Exterior Lathing 9/15/2021 Approved MARK FERRARI
Final 9/27/2021 Conditional Approval MARK FERRARI
SGSOV-Seismic Gas S/O Valve 9/27/2021 SGSOV Approved MARK FERRARI
Smoke Detectors 9/27/2021 Approved MARK FERRARI
Final 10/28/2021 OK for CofC MARK FERRARI