2140 N ALTA ST 90031
Certificate Information: 2140 N ALTA ST 90031
- Application / Permit
- 18016-10000-38096
- Plan Check / Job No.
- B18LA25360
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft story retrofit per LAMC Div 93: (4) Special Cantilever Column System
- Permit Issued
- Issued on 1/4/2021
- Issuing Office
- Current Status
- CofC Issued on 11/1/2021
Permit Application Status History
| Submitted | 11/27/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2019 | HERNAN ARREOLA |
| Corrections Issued | 1/17/2019 | HERNAN ARREOLA |
| Quality Review Completed | 1/18/2019 | SAI KHUM |
| Building Plans Picked Up | 1/28/2019 | APPLICANT |
| Plan Check Approved | 3/6/2019 | HERNAN ARREOLA |
| No Progress | 3/6/2019 | HERNAN ARREOLA |
| Plan Check Approved | 5/3/2019 | HERNAN ARREOLA |
| Issued | 1/4/2021 | APPLICANT |
| OK for CofC | 10/28/2021 | MARK FERRARI |
| CofC Issued | 11/1/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| "D" conditions | Cleared | 6/13/2019 | ANNA VAN |
| "Q" conditions | Cleared | 6/13/2019 | ANNA VAN |
| Housing rent stabilization | Cleared | 10/15/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Mokhtari Mehrdad; Lic. No.: 836891-B | 1557 WESTWOOD BLVD #165 LOS ANGELES, CA 90024 |
| Engineer | Cohan,, Behzad Barry; Lic. No.: C36291 | 321 S PALM DR BEVERLY HILLS, CA 90212 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/26/2021 | Approved | MARK FERRARI |
| Pre-Inspection | 2/8/2021 | Corrections Issued | MARK FERRARI |
| Wood Frame | 2/18/2021 | Corrections Issued | MARK FERRARI |
| Wood Frame | 2/26/2021 | Partial Approval | MARK FERRARI |
| Wood Frame | 3/11/2021 | Partial Approval | MARK FERRARI |
| Wood Frame | 3/18/2021 | Partial Approval | LANNY MERRICK |
| Deputy Wood Construction | 4/6/2021 | Approved | MARK FERRARI |
| Wood Frame | 4/6/2021 | Partial Approval | MARK FERRARI |
| Deputy Other (see comments) | 4/7/2021 | Conditional Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 4/9/2021 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 4/14/2021 | Corrections Issued | MARK FERRARI |
| Deputy Steel/Welding | 4/23/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 4/26/2021 | Conditional Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 5/6/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 5/11/2021 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 5/11/2021 | Corrections Issued | MARK FERRARI |
| Deputy Steel/Welding | 5/12/2021 | Conditional Approval | MARK FERRARI |
| Interior/Exterior Lathing | 5/17/2021 | Partial Approval | MARK FERRARI |
| Footing/Foundation/Slab | 5/27/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 6/2/2021 | Conditional Approval | MARK FERRARI |
| Wood Frame | 7/12/2021 | Not Ready for Inspection | MARK FERRARI |
| Structural Steel Frame | 8/16/2021 | Approved | MARK FERRARI |
| Wood Frame | 8/16/2021 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 8/18/2021 | Partial Approval | MARK FERRARI |
| Deputy Wood Construction | 8/25/2021 | Approved | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2021 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 9/13/2021 | Not Ready for Inspection | MARK FERRARI |
| Interior/Exterior Lathing | 9/15/2021 | Approved | MARK FERRARI |
| Final | 9/27/2021 | Conditional Approval | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 9/27/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 9/27/2021 | Approved | MARK FERRARI |
| Final | 10/28/2021 | OK for CofC | MARK FERRARI |