2141 N ALTA ST 90031
Certificate Information: 2141 N ALTA ST 90031
- Application / Permit
- 18016-10000-38095
- Plan Check / Job No.
- B18LA25359
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CH 93. INSTALL 4 (N) SCCS.
- Permit Issued
- Issued on 1/4/2021
- Issuing Office
- Current Status
- CofC Issued on 11/2/2021
Permit Application Status History
| Submitted | 11/27/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2019 | REZA HAGHIGHAT |
| Corrections Issued | 1/14/2019 | REZA HAGHIGHAT |
| Quality Review Completed | 1/18/2019 | SAI KHUM |
| Building Plans Picked Up | 1/28/2019 | APPLICANT |
| Applicant returned to address corrections | 7/24/2019 | REZA HAGHIGHAT |
| Plan Check Approved | 9/11/2019 | REZA HAGHIGHAT |
| Issued | 1/4/2021 | APPLICANT |
| OK for CofC | 10/28/2021 | MARK FERRARI |
| CofC Issued | 11/2/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 10/5/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Mokhtari Mehrdad; Lic. No.: 836891-B | 1557 WESTWOOD BLVD #165 LOS ANGELES, CA 90024 |
| Engineer | Cohan,, Behzad Barry; Lic. No.: C36291 | 321 S PALM DR BEVERLY HILLS, CA 90212 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/26/2021 | Approved | MARK FERRARI |
| Wood Frame | 2/18/2021 | Corrections Issued | MARK FERRARI |
| Wood Frame | 2/26/2021 | Partial Approval | MARK FERRARI |
| Wood Frame | 3/11/2021 | Partial Approval | MARK FERRARI |
| Wood Frame | 3/18/2021 | Partial Approval | LANNY MERRICK |
| Deputy Wood Construction | 4/6/2021 | Approved | MARK FERRARI |
| Wood Frame | 4/6/2021 | Partial Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 4/9/2021 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 4/14/2021 | Corrections Issued | MARK FERRARI |
| Interior/Exterior Lathing | 5/17/2021 | Not Ready for Inspection | MARK FERRARI |
| Interior/Exterior Lathing | 5/27/2021 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 6/17/2021 | Approved | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 6/17/2021 | Approved | MARK FERRARI |
| Footing/Foundation/Slab | 6/17/2021 | Approved | MARK FERRARI |
| Wood Frame | 7/12/2021 | Not Ready for Inspection | MARK FERRARI |
| Structural Steel Frame | 7/15/2021 | Not Ready for Inspection | MARK FERRARI |
| Deputy Steel/Welding | 8/6/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 8/13/2021 | Conditional Approval | MARK FERRARI |
| Structural Steel Frame | 8/16/2021 | Approved | MARK FERRARI |
| Wood Frame | 8/16/2021 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 8/18/2021 | Partial Approval | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2021 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 9/13/2021 | Not Ready for Inspection | MARK FERRARI |
| Interior/Exterior Lathing | 9/15/2021 | Approved | MARK FERRARI |
| Final | 9/27/2021 | Conditional Approval | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 9/27/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 9/27/2021 | Approved | MARK FERRARI |
| Final | 10/28/2021 | OK for CofC | MARK FERRARI |