858 W 80TH ST 90044
Certificate Information: 858 W 80TH ST 90044
- Application / Permit
- 18016-10000-37956
- Plan Check / Job No.
- B18LA25263
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL STEEL CANTILEVER COLUMNS AND PLYWOOD SHEARWALL.
- Permit Issued
- Issued on 6/1/2022
- Issuing Office
- Metro
- Current Status
- CofC Issued on 1/22/2024
Permit Application Status History
| Submitted | 11/26/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2019 | MANUEL MONTUFAR |
| Corrections Issued | 1/11/2019 | MANUEL MONTUFAR |
| Quality Review Completed | 1/11/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 1/23/2019 | APPLICANT |
| Plan Check Approved | 2/15/2022 | MANUEL MONTUFAR |
| Issued | 6/1/2022 | APPLICANT |
| OK for CofC | 1/17/2024 | DARRYL ARNOLD |
| CofC Issued | 1/22/2024 | WINSTON DUNNING |
Permit Application Clearance Information
| Miscellaneous | Cleared | 1/14/2022 | STEVEN WECHSLER |
| Housing rent stabilization | Cleared | 5/31/2022 | MICHAEL SOTO |
Contact Information
| Contractor | Saddick Construction Company Inc; Lic. No.: 751864-B | 1601 COLINA DR GLENDALE, CA 91208 |
| Engineer | Abedian,, Vanik; Lic. No.: S5323 | 2906 JOLLEY DR BURBANK, CA 91504 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/3/2023 | Corrections Issued | VAHE KELEDJIAN |
| Footing/Foundation/Slab | 10/11/2023 | Conditional Approval | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2023 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 11/9/2023 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 11/9/2023 | Approved | DARRYL ARNOLD |
| Wood Frame | 11/9/2023 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 11/15/2023 | Conditional Approval | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2023 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 11/21/2023 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 12/13/2023 | Approved | JACOB MYERS |
| Final | 1/5/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 1/5/2024 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 1/5/2024 | Approved | DARRYL ARNOLD |
| Final | 1/17/2024 | OK for CofC | DARRYL ARNOLD |