6745 N COLDWATER CANYON AVE 91606
Certificate Information: 6745 N COLDWATER CANYON AVE 91606
- Application / Permit
- 18016-10000-37899
- Plan Check / Job No.
- B18LA25222
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL (N) SCCS
- Permit Issued
- Issued on 5/27/2020
- Issuing Office
- Current Status
- CofC Issued on 12/16/2021
Permit Application Status History
| Submitted | 11/26/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2018 | VARAND SARKISIAN |
| Corrections Issued | 12/24/2018 | VARAND SARKISIAN |
| Quality Review Completed | 12/26/2018 | HANS SANTIAGO |
| Building Plans Picked Up | 1/2/2019 | APPLICANT |
| Plan Check Approved | 1/10/2019 | VARAND SARKISIAN |
| Issued | 5/27/2020 | APPLICANT |
| OK for CofC | 12/6/2021 | KENNETH ROBERTS |
| CofC Issued | 12/16/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 5/14/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Elrom Construction; Lic. No.: 571666-B | 22457 VENIDO ROAD WOODLAND HILLS, CA 91364 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/3/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 8/6/2021 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Shotcrete | 8/10/2021 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 8/27/2021 | Corrections Issued | JOE VELASQUEZ |
| Wood Frame | 8/27/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 9/15/2021 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 9/15/2021 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 9/15/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/15/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 9/21/2021 | No Access for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/21/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/23/2021 | Approved | JOE VELASQUEZ |
| Wood Frame | 9/27/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 10/21/2021 | Conditional Approval | KENNETH ROBERTS |
| Final | 11/16/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 11/16/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 11/16/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 12/6/2021 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 12/6/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 12/6/2021 | Approved | KENNETH ROBERTS |