255 N UNION AVE 90026
Certificate Information: 255 N UNION AVE 90026
- Application / Permit
- 18016-10000-37746
- Plan Check / Job No.
- B18LA25132
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL 3 (N) SCCS AND SHEAR WALL.
- Permit Issued
- Issued on 1/17/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 2/8/2021
Permit Application Status History
| Submitted | 11/21/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2019 | AUNG SOE |
| Corrections Issued | 1/7/2019 | AUNG SOE |
| Quality Review Completed | 1/14/2019 | SAI KHUM |
| Building Plans Picked Up | 1/17/2019 | APPLICANT |
| Plan Check Approved | 6/21/2019 | MANUEL MONTUFAR |
| Issued | 1/17/2020 | LADBS |
| OK for CofC | 10/30/2020 | DARRYL ARNOLD |
| CofC Issued | 2/8/2021 | DAVID TSAU |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 10/24/2019 | STEVEN HOFSTAD |
Contact Information
| Engineer | Shoraka,, Khojasteh Farhang; Lic. No.: C33555 | 1423 S BEVERLY GLEN UNIT A LOS ANGELES, CA 90024 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/18/2020 | Approved | BRUCE CAMPBELL |
| Deputy Reinf. Concrete | 2/19/2020 | Conditional Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 2/25/2020 | Conditional Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 3/31/2020 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 4/3/2020 | Approved | MARK FERRARI |
| Deputy Steel/Welding | 4/9/2020 | Conditional Approval | MARK FERRARI |
| Wall Anchors | 7/24/2020 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 7/24/2020 | Conditional Approval | DARRYL ARNOLD |
| Insulation | 7/29/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 7/29/2020 | Partial Inspection | DARRYL ARNOLD |
| Interior/Exterior Lathing | 8/5/2020 | Approved | DARRYL ARNOLD |
| Final | 10/23/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 10/23/2020 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 10/23/2020 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 10/23/2020 | Approved | DARRYL ARNOLD |
| Final | 10/30/2020 | OK for CofC | DARRYL ARNOLD |