1624 S 3RD AVE 90019
Certificate Information: 1624 S 3RD AVE 90019
- Application / Permit
- 18016-10000-37613
- Plan Check / Job No.
- B18LA25057
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL HARDY PANELS & WOOD SHEARWALL
- Permit Issued
- Issued on 7/8/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 7/23/2021
Permit Application Status History
| Submitted | 11/20/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2019 | VARAND SARKISIAN |
| Corrections Issued | 1/7/2019 | VARAND SARKISIAN |
| Quality Review Completed | 1/10/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 1/14/2019 | APPLICANT |
| Plan Check Approved | 11/26/2019 | VARAND SARKISIAN |
| Issued | 7/8/2020 | APPLICANT |
| OK for CofC | 6/8/2021 | MARK FERRARI |
| CofC Issued | 7/23/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| ZI | Cleared | 11/26/2019 | JOE LUCKEY |
| Housing rent stabilization | Cleared | 7/7/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Viera Design & Construction; Lic. No.: 972064-B | 17646 E BENBOW ST COVINA, CA 91722 |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/23/2020 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 8/19/2020 | Approved | DARRYL ARNOLD |
| Footing/Foundation/Slab | 8/19/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 10/30/2020 | Corrections Issued | DARRYL ARNOLD |
| Deputy Steel/Welding | 12/22/2020 | Conditional Approval | JONATHAN QUACH |
| Structural Steel Frame | 1/5/2021 | Approved | DARRYL ARNOLD |
| Wood Frame | 1/5/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Interior/Exterior Lathing | 1/19/2021 | Conditional Approval | DARRYL ARNOLD |
| Final | 2/8/2021 | Conditional Approval | MARK FERRARI |
| METHANE-Final | 2/8/2021 | Approved | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 2/8/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 2/8/2021 | Approved | MARK FERRARI |
| Final | 6/8/2021 | OK for CofC | MARK FERRARI |