4741 N CLYBOURN AVE 91602

Certificate Information: 4741 N CLYBOURN AVE 91602

Application / Permit
18016-10000-37462
Plan Check / Job No.
B18LA24915
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
soft story retrofit per LAMC Division 93: install 1 (n) sccs and 1 new shear wall.
Permit Issued
Issued on 5/10/2021
Issuing Office
Current Status
CofC Issued on 9/10/2021

Permit Application Status History

Submitted 11/19/2018 APPLICANT
Assigned to Plan Check Engineer 1/3/2019 JAIME OROZCO
Corrections Issued 1/8/2019 JAIME OROZCO
Quality Review Completed 1/9/2019 HANS SANTIAGO
Building Plans Picked Up 1/17/2019 APPLICANT
Plan Check Approved 1/29/2019 JAIME OROZCO
Issued 5/10/2021 APPLICANT
OK for CofC 8/27/2021 JOE VELASQUEZ
CofC Issued 9/10/2021 JEFFREY DURAN

Permit Application Clearance Information

Housing rent stabilization Cleared 4/20/2021 ISMAEL HERNANDEZ

Contact Information

Contractor Cal Retrofit; Lic. No.: 1022167-B 6900 CANBY AVE #108      RESEDA, CA 91335
Engineer Zohrevand,, Pedram; Lic. No.: C82328 21201 KITTRIDGE ST APT 9105      WOODLAND HILLS, CA 91303

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/21/2021 Not Ready for Inspection JOE VELASQUEZ
Deputy Drilled-In Anchors 7/8/2021 Conditional Approval JEFFREY DURAN
Deputy Other (see comments) 7/8/2021 Conditional Approval KENNETH ROBERTS
Deputy Reinf. Concrete 7/8/2021 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 7/15/2021 Approved JOE VELASQUEZ
Structural Steel Frame 7/15/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 7/15/2021 Not Ready for Inspection JOE VELASQUEZ
Deputy Reinf. Concrete 7/19/2021 No Access for Inspection JOE VELASQUEZ
Wood Frame 7/26/2021 Partial Approval JOE VELASQUEZ
Insulation 8/3/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 8/3/2021 Corrections Issued JOE VELASQUEZ
Insulation 8/9/2021 Approved JOE VELASQUEZ
Wood Frame 8/9/2021 Approved JOE VELASQUEZ
Interior/Exterior Lathing 8/13/2021 Approved JOE VELASQUEZ
Final 8/27/2021 OK for CofC JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 8/27/2021 SGSOV Approved JOE VELASQUEZ
Smoke Detectors 8/27/2021 Approved JOE VELASQUEZ