10776 W ROSE AVE 90034
Certificate Information: 10776 W ROSE AVE 90034
- Application / Permit
- 18016-10000-37372
- Plan Check / Job No.
- B18LA24840
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. VERIFY (E) RETROFIT PER 15016-30000-03424 IS IN COMPLIANCE FOR NORTH AND SOUTH ELEVATIONS. INSTALL GRADE BEAMS TO RETROFIT EAST ELEVATION..
- Permit Issued
- Issued on 1/23/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 6/22/2020
Permit Application Status History
| Submitted | 12/3/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/17/2019 | EVERARDO SANTOS |
| Corrections Issued | 1/23/2019 | EVERARDO SANTOS |
| Quality Review Completed | 1/28/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 2/1/2019 | APPLICANT |
| Plan Check Approved | 6/24/2019 | EVERARDO SANTOS |
| Issued | 1/23/2020 | LADBS |
| OK for CofC | 6/16/2020 | GRANT WOODS |
| CofC Issued | 6/22/2020 | TED RIES |
Permit Application Clearance Information
| Drainage to Storm Drain | Cleared | 2/26/2019 | OSCAR GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2019 | OSCAR GUTIERREZ |
| Housing rent stabilization | Cleared | 1/14/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Quakestrong; Lic. No.: 1037437-B | 1213 LA BREA AVENUE LOS ANGELES, CA 90019 |
| Engineer | Puliyadi,, Senthilnath Surendran; Lic. No.: C71630 | 114 SHADOWHILL CIRCLE SAN RAMON, CA 94583 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/20/2020 | Approved | NICK LAROCCA |
| Deputy Drilled-In Anchors | 3/27/2020 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 4/15/2020 | Conditional Approval | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 4/24/2020 | Approved | GRANT WOODS |
| Structural Steel Frame | 4/24/2020 | Approved | GRANT WOODS |
| Wood Frame | 4/24/2020 | Approved | GRANT WOODS |
| Deputy Reinf. Concrete | 5/4/2020 | No Access for Inspection | GRANT WOODS |
| Deputy Wood Construction | 5/11/2020 | Conditional Approval | PAUL DAVIDSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2020 | Approved | GRANT WOODS |
| Interior/Exterior Lathing | 5/21/2020 | Approved | GRANT WOODS |
| Final | 6/16/2020 | OK for CofC | GRANT WOODS |
| Smoke Detectors | 6/16/2020 | Approved | GRANT WOODS |