5022 N RIVERTON AVE 91601
Certificate Information: 5022 N RIVERTON AVE 91601
- Application / Permit
- 18016-10000-37340
- Plan Check / Job No.
- B18LA24812
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93 USING STEEL CANTILEVER COLUMNS AND WOOD SHEAR WALL .
- Permit Issued
- Issued on 8/5/2020
- Issuing Office
- Current Status
- CofC Issued on 12/17/2020
Permit Application Status History
| Submitted | 11/16/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2018 | HERNAN ARREOLA |
| Corrections Issued | 1/8/2019 | HERNAN ARREOLA |
| Quality Review Completed | 1/14/2019 | SAI KHUM |
| Building Plans Picked Up | 1/24/2019 | APPLICANT |
| Applicant returned to address corrections | 5/8/2019 | HERNAN ARREOLA |
| Plan Check Approved | 6/24/2019 | HERNAN ARREOLA |
| No Progress | 3/7/2020 | HERNAN ARREOLA |
| Plan Check Approved | 7/6/2020 | ANDREW SANTIAGO |
| Issued | 8/5/2020 | APPLICANT |
| OK for CofC | 11/20/2020 | JOE VELASQUEZ |
| CofC Issued | 12/17/2020 | JEFFREY DURAN |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 6/6/2019 | JIM URQUHART |
| Redevelopment Project Area | Cleared | 6/1/2020 | DAVID URITA |
| Historic Resource Verification | Cleared | 6/24/2020 | MICAELA TORRES-GIL |
| Housing rent stabilization | Cleared | 7/30/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Retrofitting360 Inc; Lic. No.: 1039226-B | 19562 VENTURA BLVD# 230 TARZANA, CA 91356 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/3/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 9/10/2020 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Wood Construction | 9/16/2020 | No Access for Inspection | JOE VELASQUEZ |
| Reinforced Concrete Frame | 9/16/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 9/16/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/16/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Reinforced Concrete Frame | 9/22/2020 | Corrections Issued | JOE VELASQUEZ |
| Structural Steel Frame | 9/22/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/22/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Wood Construction | 10/7/2020 | No Access for Inspection | JOE VELASQUEZ |
| Reinforced Concrete Frame | 10/7/2020 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 10/7/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 10/7/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 10/8/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Reinforced Concrete Frame | 10/8/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 10/8/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 10/8/2020 | Partial Approval | JOE VELASQUEZ |
| Structural Steel Frame | 10/13/2020 | Not Ready for Inspection | RONALD PACHECO |
| Wood Frame | 10/13/2020 | Not Ready for Inspection | RONALD PACHECO |
| Structural Steel Frame | 10/14/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 10/14/2020 | Partial Approval | JOE VELASQUEZ |
| Reinforced Concrete Frame | 10/16/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 10/16/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 10/16/2020 | Partial Approval | JOE VELASQUEZ |
| Deputy Wood Construction | 10/19/2020 | Conditional Approval | JONATHAN QUACH |
| Reinforced Concrete Frame | 10/21/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 10/21/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 10/21/2020 | Partial Approval | JOE VELASQUEZ |
| Wood Frame | 10/26/2020 | Approved | JOE VELASQUEZ |
| Reinforced Concrete Frame | 10/27/2020 | No Access for Inspection | EDWIN GREGORYONA |
| Structural Steel Frame | 10/27/2020 | No Access for Inspection | EDWIN GREGORYONA |
| Interior/Exterior Lathing | 11/2/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 11/5/2020 | Approved | JOE VELASQUEZ |
| Final | 11/20/2020 | OK for CofC | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 11/20/2020 | SGSOV Approved | JOE VELASQUEZ |
| Smoke Detectors | 11/20/2020 | Approved | JOE VELASQUEZ |