2015 S BENTLEY AVE 90025
Certificate Information: 2015 S BENTLEY AVE 90025
- Application / Permit
- 18016-10000-37186
- Plan Check / Job No.
- B18LA24736
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY SEISMIC RETROFIT PER LAMC DIV. 93:INSTALL STEEL MOMENT FRAMES
- Permit Issued
- Issued on 6/10/2021
- Issuing Office
- Metro
- Current Status
- CofC Issued on 8/11/2021
Permit Application Status History
| Submitted | 11/16/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/13/2018 | MANUEL MONTUFAR |
| Corrections Issued | 1/3/2019 | MANUEL MONTUFAR |
| Quality Review Completed | 1/14/2019 | SAI KHUM |
| Plan Check Approved | 9/6/2019 | MANUEL MONTUFAR |
| Issued | 6/10/2021 | APPLICANT |
| OK for CofC | 8/9/2021 | JOHN DODGE |
| CofC Issued | 8/11/2021 | TED RIES |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 5/26/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Lupu Iancu; Lic. No.: 580850-B | 1420 NORTH ALTA VISTA #213 LOS ANGELES, CA 90046 |
| Engineer | Jones,, Richard Alan; Lic. No.: S4977 | 5058 VIA INGRESSO YORBA LINDA, CA 92886 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/23/2021 | Approved | GRANT WOODS |
| Pre-Inspection | 7/9/2021 | Approved | PAUL DAVIDSON |
| Deputy Steel/Welding | 7/16/2021 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 7/19/2021 | Conditional Approval | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 7/23/2021 | Approved | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 7/23/2021 | No Access for Inspection | SORIN CIRSTOIU |
| Structural Steel Frame | 7/23/2021 | No Access for Inspection | SORIN CIRSTOIU |
| Structural Steel Frame | 7/23/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Structural Steel Frame | 7/29/2021 | Approved | PAUL DAVIDSON |
| Wood Frame | 7/29/2021 | Approved | PAUL DAVIDSON |
| Interior/Exterior Lathing | 8/2/2021 | Approved | PAUL DAVIDSON |
| Final | 8/6/2021 | Conditional Approval | JOHN DODGE |
| METHANE-Final | 8/6/2021 | Approved | JOHN DODGE |
| SGSOV-Seismic Gas S/O Valve | 8/6/2021 | SGSOV Approved | JOHN DODGE |
| Smoke Detectors | 8/6/2021 | Approved | JOHN DODGE |
| Final | 8/9/2021 | OK for CofC | JOHN DODGE |