2630 S BEDFORD ST 90034
Certificate Information: 2630 S BEDFORD ST 90034
- Application / Permit
- 18016-10000-36982
- Plan Check / Job No.
- B18LA24515
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING SINGLE FAMILY DWELLING INTO AN ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. MUST FINAL 18014-10000-03177 SIMULTANEOUSLY WITH CURRENT PERMIT. ***SEE COMMENTS***
- Permit Issued
- Issued on 6/20/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2018 | MICHAEL LOPEZ |
| Corrections Issued | 12/3/2018 | MICHAEL LOPEZ |
| Quality Review Completed | 12/6/2018 | FELIX FIGUEROA |
| Building Plans Picked Up | 1/14/2019 | APPLICANT |
| Green Plans Picked Up | 6/18/2019 | APPLICANT |
| Plan Check Approved | 6/20/2019 | MICHAEL LOPEZ |
| Issued | 6/20/2019 | LADBS |
| CofO in Progress | 5/5/2021 | EVAN COOPER |
| CofO in Progress | 5/5/2021 | EVAN COOPER |
| Permit Finaled | 5/13/2021 | KENNETH NAGLE |
| CofO Issued | 5/13/2021 | KENNETH NAGLE |
| Permit Finaled | 5/13/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2019 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2019 | ADRIAN SANCHEZ |
| ZA Case | Cleared | 6/10/2019 | JOE LUCKEY |
| Green Code | Cleared | 6/18/2019 | COLIN LOREDO |
Contact Information
| Architect | Carmichael,, Elizabeth Joan; Lic. No.: C31130 | 2640 FINANCIAL COURT SUITE D SAN DIEGO, CA 92117 |
| Contractor | Hildebrandt Contracting And Development; Lic. No.: 865585-B | 4157 NEOSHO AVE LOS ANGELES, CA 90066 |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| HVAC-Rough | 7/17/2020 | Partial Approval | JUAN VALENZUELA |
| Insulation | 7/17/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Interior/Exterior Lathing | 7/17/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| MERV13>=Rough | 7/17/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Sewer | 7/17/2020 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 8/28/2020 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 9/2/2020 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 9/17/2020 | Not Ready for Inspection | EVAN COOPER |
| Shower Pan | 9/17/2020 | Corrections Issued | EVAN COOPER |
| Special/Order Compliance | 2/5/2021 | Approved | EVAN COOPER |
| Special/Order Compliance | 2/19/2021 | Corrections Issued | KENNETH NAGLE |
| BUILDING-Rough-Frame | 2/22/2021 | Approved | EVAN COOPER |
| Final | 2/22/2021 | Conditional Approval | EVAN COOPER |
| Green Building Final | 2/22/2021 | Approved | EVAN COOPER |
| Green Building Rough | 2/22/2021 | Approved | EVAN COOPER |
| MERV13>=Final | 2/22/2021 | Approved | EVAN COOPER |
| MERV13>=Rough | 2/22/2021 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 2/22/2021 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 2/22/2021 | Approved | EVAN COOPER |
| Final | 5/5/2021 | OK to Issue CofO | EVAN COOPER |